Croatia to launch Krk terminal with US LNG?

Croatia’s long-awaited LNG import terminal on the island of Krk in the northern Adriatic Sea could receive its first commercial cargo from the US.

The BP-chartered 155,000-cbm Tristar Ruby left the Dominion Cove Point facility in Maryland on Saturday and its AIS data shows that it would arrive at the Krk facility on January 1.

LNG Croatia, the state-owned Krk terminal developer previously said it planned to start commercial operations on January 1.

To remind, Croatia’s first FSRU arrived at the facility earlier this month after picking up a small commissioning cargo from Sagunto in Spain.

Besides the FSRU, the import facility consists of a jetty and a high-pressure gas pipeline.

Croatia’s first LNG terminal will have a capacity to send up to 2.6 bcm per year of natural gas into the national grid.

Furthermore, the terminal developer said earlier this year that three firms booked all of the terminal’s capacities for the next three years.

The capacity takers include Hungary’s state-owned MFGK and trading firm MET.

Additionally, Hungary said in September the country signed a deal with LNG giant Shell to receive natural gas via the Krk facility as part of the MFGK booking.

Qatar’s PowerGlobe, the energy arm of privately-held Optimized Holding, booked the largest capacity at Krk spanning a period of 15 years.

Croatia’s LNG import project costs 233.6 million euros ($286 million) with EU providing 101.4 million euros from the Connecting Europe Facility.

Most Popular

Eni seeks contractors for third Mozambique FLNG

Italian energy firm Eni and its partners in the Mozambique Rovuma Venture have invited companies to submit their expression of interest for the construction of one large floating LNG production unit with a capacity of up to 6 mtpa.

Seaspan, Stabilis terminate charter deal for LNG bunkering vessel

Canada's Seaspan Energy has exercised an option to terminate its previously signed charter agreement with Houston-based small-scale LNG player Stabilis Solutions for the 7,500-cbm LNG bunkering vessel Seaspan Garibaldi.

Golden Pass LNG gets green light to start commissioning of second train

Golden Pass LNG, a joint venture of energy giants QatarEnergy and ExxonMobil, has secured approval from the US FERC to kick off the commissioning process for the second liquefaction train at its three-train plant in Texas.

More News Like This

Croatian FSRU wraps up 600th truck loading op

State-owned LNG Croatia, the operator of the FSRU-based Krk import facility, has completed the 600th LNG reloading operation directly from the vessel to a truck.

Bosnia and Croatia seal LNG pipeline deal

Bosnia and Herzegovina and Croatia signed an agreement to construct a US-backed pipeline which will allow Bosnia to receive US liquefied natural gas (LNG) via Croatia's FSRU-based import terminal on the island of Krk.

Croatian FSRU gets first Tortue LNG cargo

Croatia's FSRU-based LNG import facility on the northern Adriatic island of Krk has received its first cargo from the BP-operated Greater Tortue Ahmeyim LNG project offshore Mauritania and Senegal.

Cove Point LNG seeks OK for re-exports

Berkshire Hathaway’s Cove Point LNG, the operator of the LNG export and import facility in Maryland, is seeking a renewal of its authorization from the US DOE to re-export previously imported LNG.