Freeport LNG says second LNG jetty ready to return to service

Freeport LNG, the operator of the three-train 15 mtpa liquefaction plant in Texas, is ready to place back into service its second jetty.

In October, Freeport received approval from the US FERC to start commissioning its second jetty.

The commissioning and cooldown included the Loop 2 transfer piping, Dock, 2 and the recirculation piping.

In order to continue Freeport’s sequential plan to return the LNG export facility to full commercial operations, Freeport now requests authorization from FERC to place Loop 2 and Dock 2 back into service, according to a filling dated November 17.

“We anticipate nitrogen cooldown to be completed in the next few days, which will then be followed by introduction of hydrocarbons (i.e., LNG) in order to re-inventory the Loop 2 piping system,” Freeport said.

Freeport anticipates having the Loop 2 system inventoried on or about November 21st.

“Given this, Freeport would greatly appreciate FERC’s response to this request on November 21st so that Dock 2 can be returned to service,” it said.

Any return to service would only proceed after the successful and safe completion of Loop 2 cooldown and re-inventorying, Freeport said.

Third tank remains idled

The LNG terminal operator noted that any authorization pursuant to this request will be limited to returning Loop 2 and Dock 2 to service and will not include the return to service of any other equipment at its facilities that remain idled from the June 8, 2022 incident, such as Tank 3.

In February this year, the LNG terminal operator shipped the first cargo from its LNG export plant in Texas since the shutdown in June 2022.

Freeport LNG received approvals from both FERC and PHMSA during the first quarter to restart Phase I operations.

These consist of three trains, two LNG storage tanks (tanks 1 and 2), and a single LNG jetty (dock 1).

Most Popular

Colombia’s Ecopetrol ditches LNG import tenders

Colombia’s state-owned energy firm Ecopetrol has rejected five-year liquefied natural gas (LNG) supply offers, saying that the minimum commercial conditions were not met.

Petrovietnam units plan new LNG-to-power project

PV Power and PV Gas, units of state-owned Petrovietnam, signed cooperation agreements to secure gas supplies for power plants in southwestern Vietnam and explore developing an integrated liquefied natural gas (LNG) project in the northern port city of Hai Phong.

Poland’s Gaz-System moves forward with Gdansk LNG jetty work

Poland’s state-owned LNG terminal operator, Gaz-System, is advancing construction of the jetty which will host the first floating storage and regasification unit (FSRU) for its LNG import project in Gdansk.

More News Like This

US FERC launches first LNG authorization program

The US Federal Energy Regulatory Commission (FERC) proposed accelerating liquefied natural gas (LNG) infrastructure development through a blanket authorization program.

Venture Global gets approval to place first Plaquemines LNG phase in service

Venture Global’s Plaquemines LNG has secured approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

Cheniere’s Corpus Christi Trains 8 and 9 project 55.6 percent complete

US LNG exporter Cheniere continues to progress construction on its Corpus Christi Midscale Trains 8 and 9 project in Texas.

Venture Global seeks FERC OK to place first Plaquemines LNG phase in service

Venture Global's Plaquemines LNG is seeking approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.