Golden Pass LNG construction moving forward

QatarEnergy and ExxonMobil released the latest construction update for their giant Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

Golden Pass LNG construction moving forward
Utility generators (Image: Golden Pass)

First train expected to start ops in 2024

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas, continued piping and vessels insulation activities and helical piles and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins.

As per the pipeline expansion project, Golden Pass continued civil activities and concrete foundation pours at milepost MP33 and MP69 compressor stations and also continued pipe fabrication and installation at these stations.

It also continued construction activities of the Sabine Spur, Natural Gas Pipeline (NGPL)
Interconnect improvements, and associated facilities.

Golden Pass LNG construction moving forward
MP33 compressor station (Image: Golden Pass)

As per the start of operations, the FERC said in an inspection report earlier this month that the anticipated in-service timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

The anticipated in-service timing for the pipeline expansion project is expected sometime prior to the second half of 2024, it said.

The US currently exports LNG via Cheniere’s Sabine Pass and Corpus Christi plants, Sempra’s Cameron LNG terminal, Venture Global’s Calcasieu Pass facility, the Freeport LNG terminal, Berkshire Hathaway’s Cove Point terminal, and Kinder Morgan’s Elba Island facility.

Besides the Golden Pass LNG export plant, Venture Global’s Plaquemines LNG facility is also expected to start production next year.

Most Popular

Shell makes executive changes

UK-based LNG giant Shell has appointed two new directors after Huibert Vigeveno, downstream, renewables, and energy solutions director, decided...

Venture Global LNG raises $1.75 billion in IPO

Venture Global announced on Thursday the pricing of its IPO of 70 million shares of its Class A common...

Kinder Morgan to build $1.7 billion Texas LNG pipeline

Kinder Morgan CEO Kim Dang announced this in the company's fourth-quarter results report on Wednesday. Dang said the project is...

More News Like This

Kinder Morgan to build $1.7 billion Texas LNG pipeline

Kinder Morgan CEO Kim Dang announced this in the company's fourth-quarter results report on Wednesday. Dang said the project is...

Hudong-Zhonghua delivers new QatarEnergy LNG carrier

China's Hudong-Zhonghua has delivered another 174,000-cbm liquefied natural gas (LNG) carrier built as part of the massive QatarEnergy shipbuilding...

Chart seals LNG equipment deal with ExxonMobil

This enabling agreement sets the terms, conditions, and commercial framework for Chart to provide LNG equipment, technology, and services...

Chevron-led JV secures GHG permit near Barrow Island

US energy giant Chevron and its partners Shell and ExxonMobil have been awarded the greenhouse gas (GHG) assessment permit...