Golden Pass LNG construction moving forward

QatarEnergy and ExxonMobil continue to make progress in building their giant Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mpta and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains next to the existing LNG import terminal.

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.

Golden Pass LNG export terminal
Second LNG train (Image: Golden Pass)

First LNG supplies in 2024

Golden Pass and its contractors progressed installation of piping and steel in process areas, continued walls and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins.

The firm also continued LNG tank tops modifications and progressed cable tray installations and cable pulling activities.

As per the pipeline expansion project, Golden Pass continued civil and construction activities supporting milepost (MP)01 Compressor Station, Sabine Spur, Natural Gas Pipeline (NGPL) Interconnect improvements, and associated facilities.

FERC said in an inspection report last month that the anticipated in-service timing for the first train is the second half of 2024, with the second and the third train following after.

The regulator said in inspections reports earlier this year that the anticipated in-service timing for the first train was the first quarter of 2024.

QatarEnergy’s CEO Saad Sherida Al-Kaabi said this week in Vancouver during LNG 2023 that 40 percent of all the new LNG supplies that will come to the market by 2029, will be from QatarEnergy’s projects.

He said that QatarEnergy is increasing production to 126 million tons per annum in Qatar and “we have another 16-18 MTPA out of the US coming online next year.”

Most Popular

Golar’s fourth unit may be world’s largest FLNG

Golar LNG's next converted FLNG may have a capacity of 5 mtpa, which would make it the world's largest FLNG, according to CEO Karl Staubo.

Sempra eyes Port Arthur LNG expansion FID in 2025

Sempra Infrastructure, a unit of Sempra, expects to make a final investment decision on the second phase of its Port Arthur LNG export project in Texas in 2025.

Venture Global to introduce gas to 9th Plaquemines liquefaction block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the ninth liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

More News Like This

Hanwha Ocean delivers 200th LNG carrier

South Korea's Hanwha Ocean has delivered its 200th liquefied natural gas (LNG) carrier.

Sicim bags Rovuma LNG gig

Italy's Sicim has secured a contract from Subsea 7 for the ExxonMobil-led Rovuma LNG project in Mozambique.

Construction advances on Golden Pass LNG terminal

Energy giants QatarEnergy and ExxonMobil and their contractors continue to move forward with the construction work on the Golden Pass LNG export facility in Texas.

TotalEnergies CEO says partners working hard on Papua LNG

TotalEnergies has a 37.55 percent operating stake in the Papua LNG project, ExxonMobil has 37.04 percent, Santos owns a...