LNG Canada pipeline almost 75 percent complete

TC Energy’s Coastal GasLink project, which will supply natural gas to the Shell-led LNG Canada export terminal, continues to progress with the construction of the pipeline in British Columbia.

Coastal GasLink said in a statement on September 20 announcing the completion of its Wilde Lake compressor facility that the pipeline has approached 75 percent overall completion. The overall progress reached 69 percent as of the end of July.

According to the firm, the Wilde Lake facility near Dawson Creek in northeastern BBC would serve as the starting point for the natural gas pipeline, compressing the gas to provide the pressure required to safely deliver the gas all the way to LNG Canada’s site in Kitimat.

It has the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023.

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

LNG carrier arrives to load first LNG Canada cargo

The 174,000-cbm GasLog Glasgow has arrived at the LNG Canada jetty in Kitimat to load the first LNG cargo produced at the Shell-led terminal, an LNG Canada spokesperson told LNG Prime on Saturday.

HD Hyundai Samho scores contract to build LNG carrier quartet

South Korea’s HD Hyundai Samho has secured an order to build four liquefied natural gas (LNG) carriers for about $1.03 billion.

Coastal Bend LNG plans large Texas export plant

Coastal Bend LNG said it had initiated development of a 22.5 million ton per annum (mtpa) natural gas liquefaction and export facility on the Texas Gulf Coast.

More News Like This

LNG carrier arrives to load first LNG Canada cargo

The 174,000-cbm GasLog Glasgow has arrived at the LNG Canada jetty in Kitimat to load the first LNG cargo produced at the Shell-led terminal, an LNG Canada spokesperson told LNG Prime on Saturday.

Shell denies BP takeover talks

UK-based LNG giant Shell denied it was in talks to buy BP following media reports.

Nordsol in bio-LNG production milestone

Nordsol said that the three operational bio-LNG plants in the Netherlands and the UK, which utilize its technology, have collectively surpassed the 10,000-ton mark in bio-LNG production.

Shell’s LNG Canada achieves first LNG

LNG giant Shell has started production at the first liquefaction train at its LNG Canada export terminal in Kitimat, an LNG Canada spokesperson told LNG Prime on Sunday.