LNG Canada’s new tug berth to be completed in early 2024

A new tug berth being built for the Shell-led LNG Canada export project will be ready in early 2024 to welcome a fleet of dual-fuel and electric tugs.

Construction of the tug berth facility started in early 2023 and is scheduled to be fully completed in early 2024, LNG Canada said in a statement issued last week.

Bridgemans Kitamaat Joint Venture, a Haisla Nation partnership, has secured the new engineering, procurement, and construction contract award which includes the installation of marine piles, floating docks, and a breakwater.

LNG Canada says the new tug berth is essential to operation of the escort tugs and harbor tugs that will provide ship-assist and escort towing services to LNG carriers calling at LNG Canada’s export facility.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

LNG Canada's new tug berth to be completed in early 2024
Image: LNG Canada

HaiSea Marine, majority-owned by the Haisla Nation in partnership with Canada’s Seaspan ULC, has a major contract with LNG Canada to build and operate escort and harbor tugs required for the LNG export project worth more than $30 billion.

The new fleet of tugs will consist of two RAstar 4000-DF escort dual-fuel tugs that will run on LNG and also diesel.

Moreover, the fleet also includes three ElectRA 2800 electric tugs.

Turkey’s Sanmar is building the tugs designed by Vancouver BC-based naval architect company, Robert Allan.

Earlier this year, Sanmar launched the first of two LNG dual-fuel tugs that will feature Wartsila engines.

Also, Norway’s Corvus Energy won a contract to deliver batteries to the three electric tugs.

- Advertisements -

Most Popular

Golar buys vessel for third FLNG project

Golar LNG has exercised its option to acquire the 148,000-cbm Moss-type carrier, Fuji LNG, which it aims to convert...

Australia’s Woodside investigating Pluto LNG incident

Australian LNG player Woodside has launched an investigation following an incident that took place on Friday at its Pluto...

Gas leak shuts Equinor’s Hammerfest LNG terminal

Norway's Equinor has closed its 4.3 mtpa Hammerfest LNG export plant due to a gas leak. "I can confirm that...

More News Like This

FueLNG’s second bunkering vessel wraps up loading op

Singapore’s FueLNG, a joint venture consisting of Shell and Sembcorp Marine’s Keppel Offshore & Marine, said that its second...

Worley lands Shell contract

A unit of LNG giant Shell has awarded Australian engineering firm Worley an enterprise framework agreement to provide services...

Shell to supply first LNG cargo to PetroVietnam Gas

PetroVietnam Gas, a unit of state-owned PetroVietnam, said that its Thi Vai LNG import terminal will receive the first...

First electric tug ready to start serving LNG Canada

HaiSea Marine's first of three electric tugboats which will serve the Shell-led LNG Canada project is on its way...