QatarEnergy and ExxonMobil update on Golden Pass LNG work

QatarEnergy and ExxonMobil continue to make progress in building their $10 billion Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mpta and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the trains next to the existing LNG import terminal.

“Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water
protection, levee construction, stockpiling of material, and piling,” Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Brownfield piperack (Image: Golden Pass)

First train in 2024

Golden Pass and its contractors progressed installation of piping and steel in process areas, continued walls and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass continued fin fan installation in the Train 1 main piperack and progressed setting various vessels on respective foundations and continued preparatory activities for Brownfield tie-ins and LNG tanks top modifications scope.

The firm said that structural steel installation continued around the brownfield boil-off gas compressors.

According to Golden Pass, it started precommissioning activities as well.

As per the pipeline expansion project, Golden Pass continued construction activities for the new 24-inch-diameter Sabine pipeline spur, and started mobilization and civil activities at the milepost (MP) 33 and MP69 compressor station areas.

FERC said in an inspection report last month that the anticipated in-service timing for the first train is the first quarter of 2024, the third quarter of 2024 for the second train, and the first quarter of 2025 for the third train.

- Advertisements -

Most Popular

Golden Pass LNG to ramp up construction activities after Zachry deal

QatarEnergy and ExxonMobil will ramp up construction activities at the Golden Pass LNG export terminal in Texas after a...

Tellurian updates on Driftwood LNG work

US LNG terminal developer Tellurian, which is being acquired by Australia's Woodside, released the latest construction update for the...

Hudong-Zhonghua confirms TotalEnergies order for LNG bunkering vessel

China’s Hudong-Zhonghua said it had secured an order to build one 18,600-cbm LNG bunkering vessel for French energy giant...

More News Like This

Golden Pass LNG to ramp up construction activities after Zachry deal

QatarEnergy and ExxonMobil will ramp up construction activities at the Golden Pass LNG export terminal in Texas after a...

GTT bags order for 10 giant LNG carriers

French LNG containment giant GTT has secured an order from China's Hudong-Zhonghua for ten 271,000-cbm liquefied natural gas carriers. GTT...

Golden Pass LNG to speed up pipeline construction

QatarEnergy and ExxonMobil are seeking approval from US energy regulators to increase the peak workforce to speed up the...

Japan’s Chiyoda provides Golden Pass LNG update

Japan's engineer Chiyoda has released an update regarding the construction of the Golden Pass LNG export project in Texas,...