QatarEnergy and ExxonMobil update on Golden Pass LNG work

QatarEnergy and ExxonMobil continue to make progress in building their $10 billion Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mpta and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the trains next to the existing LNG import terminal.

“Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water
protection, levee construction, stockpiling of material, and piling,” Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Brownfield piperack (Image: Golden Pass)

First train in 2024

Golden Pass and its contractors progressed installation of piping and steel in process areas, continued walls and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass continued fin fan installation in the Train 1 main piperack and progressed setting various vessels on respective foundations and continued preparatory activities for Brownfield tie-ins and LNG tanks top modifications scope.

The firm said that structural steel installation continued around the brownfield boil-off gas compressors.

According to Golden Pass, it started precommissioning activities as well.

As per the pipeline expansion project, Golden Pass continued construction activities for the new 24-inch-diameter Sabine pipeline spur, and started mobilization and civil activities at the milepost (MP) 33 and MP69 compressor station areas.

FERC said in an inspection report last month that the anticipated in-service timing for the first train is the first quarter of 2024, the third quarter of 2024 for the second train, and the first quarter of 2025 for the third train.

- Advertisements -

Most Popular

Worley clinches EPC contract for Venture Global’s CP2 LNG project

Australian engineering firm Worley has secured a reimbursable engineering, procurement, and construction (EPC) contract for the first phase of...

Cheniere’s Corpus Christi LNG expansion project almost 50 percent complete

US LNG exporting giant Cheniere and compatriot Bechtel are moving forward with the construction work on the expansion phase...

Japan’s MOL wins ClassNK OK for ammonia FSRU

Japan's shipping giant MOL and compatriot Mitsubishi Shipbuilding, a unit of Mitsubishi Heavy Industries, have won an approval in...

More News Like This

QatarEnergy, ExxonMobil expect first LNG from Golden Pass plant in H1 2025

Energy giants QatarEnergy and ExxonMobil are expecting to start LNG production at their Golden Pass LNG export terminal on...

QatarEnergy takes over all marketing activities from QatarEnergy LNG

LNG giant QatarEnergy has completed the previously announced integration of all marketing and related activities formerly managed by its...

Construction progress continues on Golden Pass LNG export plant

Energy giants QatarEnergy and ExxonMobil released the latest construction update for their Golden Pass liquefied natural gas (LNG) export...

GTT scores contract from HD Hyundai Heavy for 17 LNG carriers

French LNG containment giant GTT has won a large order from South Korea’s HD Hyundai Heavy Industries to design...