Qatargas kicks off work on four giant LNG trains

LNG producer Qatargas, a unit of QatarEnergy, said it has started construction on four giant LNG trains in the Ras Laffan complex, as part of the $28.75 billion North Field East project.

Qatargas announced this via its social media channels on Sunday.

QatarEnergy, previously known as Qatar Petroleum, took a final investment decision on the LNG expansion project in February this year.

A joint venture consisting of Chiyoda and Technip won the key onshore engineering, procurement and construction contract.

The four trains will have a capacity of 8 mtpa, each. This first phase of the expansion project will increase Qatar’s LNG production capacity from 77 to 110 mtpa.

QatarEnergy expects to start production in the fourth quarter of 2025.

The LNG giant also plans a second phase to further boost capacity to total 126 mtpa by 2027, as well as additional expansions.

Qatargas already operates in total fourteen LNG trains at Ras Laffan.

Most Popular

TotalEnergies board backs CEO Pouyanne for another term

French energy giant and LNG player TotalEnergies said ​on Friday that ‌its board unanimously ​backed ​the renewal of ⁠chairman ​and ​CEO Patrick Pouyanne's mandate.

NextDecade’s Rio Grande LNG gets FERC OK to boost capacity

US LNG developer NextDecade has secured a green light from the Federal Energy Regulatory Commission to increase approved capacity at its Rio Grande LNG terminal in the Port of Brownsville, Texas.

Roof raised on German LNG tank

Dutch gas grid operator Gasunie and German energy firm RWE have completed raising the roof on the first LNG storage tank at the German government-backed onshore LNG import terminal in Brunsbüttel.

More News Like This

Edison says QatarEnergy extends force majeure until early December

Italian energy firm Edison, a unit of EDF, said it received a new force majeure notification from state-owned LNG giant QatarEnergy, affecting supplies scheduled for delivery at the Adriatic LNG terminal in Italy until the beginning of December.

QatarEnergy CEO says damaged Ras Laffan LNG trains to take three years to repair

State-owned LNG giant QatarEnergy expects the damage to two liquefaction trains at its giant Ras Laffan complex to take three years to repair, according to Qatar’s energy minister and CEO of QatarEnergy, Saad Sherida Al-Kaabi.

Pakistan set to receive Qatari LNG cargo

Pakistan is set to receive a liquefied natural gas (LNG) cargo from Qatar via the Strait of Hormuz, according to shipping data.

Edison says QatarEnergy extends force majeure until early November

Italian energy firm Edison, a unit of EDF, said it had received a new force majeure notification from state-owned LNG giant QatarEnergy, affecting supplies scheduled for delivery at the Adriatic LNG terminal in Italy until early November.