RWE: Brunsbuettel FSRU to start supplying gas to grid next week

German energy firm RWE expects the 170,000-cbm FSRU Hoegh Gannet, which serves the Elbehafen LNG import terminal in Brunsbuettel, to start supplying small quantities of natural gas to the grid next week.

The FSRU, which the German government chartered from Hoegh LNG, returned to its location in Brunsbuettel after RWE moved the vessel earlier this month due to complaints by local residents on loud noise coming from the unit.

Prior to this, the FSRU-based terminal, Germany’s third such facility, received its first LNG tanker on February 14 from UAE’s Adnoc.

Hoegh Gannet will initially operate at the Brunsbuettel Port’s existing dangerous goods berth.

From the end of 2023, the FSRU will work from a new jetty to the west of the Elbehafen and Brunsbuettel Ports will build and operate this jetty.

LPG and LNG unloading

A spokesman for RWE told LNG Prime on Thursday that the onshore technical infrastructure, including hot water supply, will be completed on March 17.

“Next weekend, the first unloading of liquefied petroleum gas (LPG) for an existing customer of Brunsbuettel Ports will take place across the Hoegh Gannet according to the ship-to-ship principle,” he said.

Previously, the partners planned that the initial regasification and subsequent test phase to take place in parallel with the LPG discharge.

“Because the simultaneous commissioning of LPG unloading and LNG regasification is a very complex procedure, RWE, ship operator Hoegh, and gas grid operator Gasunie have jointly decided to complete the LPG unloading first,” the spokesman said.

“On Monday, March 20, Gasunie will fill the last section of the pipeline connecting to the FSRU with gas so that the first regasification can then begin,” he said.

Launch of ops still expected in March

The spokesman confirmed that RWE still expects the FSRU to be in “regular operation” from the end of March.

It is not yet clear when the next cargo would arrive at the unit.

The Elbehafen LNG terminal will become the third operational FSRU-based terminal in Germany and the second out of five backed by the German government after the Wilhelmshaven facility.

In January, Deutsche Regas officially launched its FSRU-based LNG import terminal in Lubmin, Germany’s second such facility and the first private terminal.

New state-owned firm Deutsche Energy Terminal GmbH will operate the five government-backed FSRUs.

Most Popular

Galp wins Calcasieu Pass arbitration against Venture Global

Portuguese energy firm Galp has won an arbitration case against US LNG exporter Venture Global LNG over LNG sales from the Calcasieu Pass plant in Louisiana.

MISC to order five more LNG carriers for Petronas charter

Malaysian shipping firm MISC will order five additional newbuild 174,000-cbm liquefied natural gas (LNG) carriers at China's Hudong-Zhonghua. The vessels will serve a 20-year charter with a unit of MISC's parent, Petronas.

Singapore LNG kicks off work on third jetty

State-owned LNG terminal operator Singapore LNG has officially kicked off the construction of a new LNG jetty, which will support the further growth of LNG bunkering in Singapore.

More News Like This

Roof raised on German LNG tank

Dutch gas grid operator Gasunie and German energy firm RWE have completed raising the roof on the first LNG storage tank at the German government-backed onshore LNG import terminal in Brunsbüttel.

German customs awards maintenance gig for LNG-powered vessels

The German Federal Customs Administration has awarded a contract to Rheinmetall to carry out repair and maintenance work on four LNG-powered vessels.

DET: FSRU returns to Stade

The 2021-built 174,000-cbm FSRU Energos Force has returned to Germany’s Stade as state-owned LNG terminal operator DET prepares to launch its fourth FSRU-based LNG import facility in Germany.

Adnoc, RWE working on up to two LNG supply deals

UAE’s ADNOC and German energy firm RWE have signed a letter of intent to progress up to two liquefied natural gas (LNG) sale and purchase agreements.