RWE: Brunsbuettel FSRU to start supplying gas to grid next week

German energy firm RWE expects the 170,000-cbm FSRU Hoegh Gannet, which serves the Elbehafen LNG import terminal in Brunsbuettel, to start supplying small quantities of natural gas to the grid next week.

The FSRU, which the German government chartered from Hoegh LNG, returned to its location in Brunsbuettel after RWE moved the vessel earlier this month due to complaints by local residents on loud noise coming from the unit.

Prior to this, the FSRU-based terminal, Germany’s third such facility, received its first LNG tanker on February 14 from UAE’s Adnoc.

Hoegh Gannet will initially operate at the Brunsbuettel Port’s existing dangerous goods berth.

From the end of 2023, the FSRU will work from a new jetty to the west of the Elbehafen and Brunsbuettel Ports will build and operate this jetty.

LPG and LNG unloading

A spokesman for RWE told LNG Prime on Thursday that the onshore technical infrastructure, including hot water supply, will be completed on March 17.

“Next weekend, the first unloading of liquefied petroleum gas (LPG) for an existing customer of Brunsbuettel Ports will take place across the Hoegh Gannet according to the ship-to-ship principle,” he said.

Previously, the partners planned that the initial regasification and subsequent test phase to take place in parallel with the LPG discharge.

“Because the simultaneous commissioning of LPG unloading and LNG regasification is a very complex procedure, RWE, ship operator Hoegh, and gas grid operator Gasunie have jointly decided to complete the LPG unloading first,” the spokesman said.

“On Monday, March 20, Gasunie will fill the last section of the pipeline connecting to the FSRU with gas so that the first regasification can then begin,” he said.

Launch of ops still expected in March

The spokesman confirmed that RWE still expects the FSRU to be in “regular operation” from the end of March.

It is not yet clear when the next cargo would arrive at the unit.

The Elbehafen LNG terminal will become the third operational FSRU-based terminal in Germany and the second out of five backed by the German government after the Wilhelmshaven facility.

In January, Deutsche Regas officially launched its FSRU-based LNG import terminal in Lubmin, Germany’s second such facility and the first private terminal.

New state-owned firm Deutsche Energy Terminal GmbH will operate the five government-backed FSRUs.

Most Popular

Celsius takes delivery of new LNG tanker

South Korea’s Samsung Heavy Industries has handed over a new 180,000-cbm LNG carrier to Denmark’s Celsius Tankers, a unit...

CEO: TotalEnergies looking to restart Mozambique LNG by end of 2024

Pouyanne discussed the Mozambique LNG project during TotalEnergies’ strategy and outlook presentation in New York on Wednesday. According to the...

Hanwha Ocean to build FSRU for $413 million

Hanwha Ocean revealed the order on Wednesday, saying it would build the unit for an unidentified Asian owner. The delivery...

More News Like This

Deutsche ReGas offers Mukran regas slots

On October 9, Deutsche ReGas will market LNG regasification capacity for the lastquarter of 2024 for the “Deutsche Ostsee”...

Gasunie, RWE plan to launch German onshore LNG terminal in 2027

In 2022, Gasunie joined forces with the German government and RWE to build the LNG import terminal, which is worth about...

Venture Global’s LNG newbuild duo to deliver first cargoes to Germany

These are the first two of nine LNG carriers Venture Global has on order in South Korea. In June this...

Germany’s DET says to launch two FSRU terminals before winter

„We are working at full speed and getting closer to the point,“ a DET spokesman said. „We expect both terminals...