TGE Gas: roofs raised on two Huizhou LNG tanks in China

Germany-based TGE Gas Engineering, a unit of China’s CIMC, said it has raised the roofs on two large storage tanks at Guangdong Energy’s Huizhou LNG terminal in China.

Each of the two tanks has a capacity of 200,000 cbm.

TGE Gas said in a statement on Thursday it is working on the EPC contract revealed last year with its consortium partner CIMC EnTech.

The LNG terminal, developed by Guangdong Huizhou LNG, has a capacity of 6.1 mtpa and consists of three 200,000-cbm LNG tanks.

TGE Gas expects the mechanical completion of the project on January 31, 2024.

Guangdong Energy previously said the total costs for the first phase of the terminal would reach about $1 billion.

Most Popular

Atlantic LNG shipping rates rise to four-month high

Atlantic LNG freight rates rose to $25,750 per day this week, while European prices also increased compared to the prior week.

Capital sells LNG carrier for scrap

Greece's Capital Gas has sold one steam liquefied natural gas (LNG) carrier for scrap, according to brokers.

US approves financing for Mozambique LNG

The Export-Import Bank of the United States has approved financing for the TotalEnergies-led Mozambique LNG project.

More News Like This

Poland expands LNG import terminal

Gaz-System and Germany-based contractor TGE Gas Engineering announced the arrival of the first LNG cargo at the new jetty...

China’s Huizhou LNG terminal gets commissioning cargo

The 145,700-cbm Maran Gas Coronis, owned by Maran Gas and Nakilat, has delivered 64,000 tons of LNG from the...

TGE Gas: Huizhou LNG tanks completed

Three 200,000-cbm LNG tanks at Guangdong Energy’s Huizhou LNG terminal in China have reached mechanical completion, according to Germany-based...

TGE Gas clinches LNG terminal job from China’s Shenzhen Gas

A unit of Germany-based TGE Gas Engineering has secured an EPC contract from China's city gas distributor Shenzhen Gas...