Venture Global nears first LNG cargo from Calcasieu Pass

Venture Global LNG’s Calcasieu Pass export project in Louisiana continues to progress towards first LNG production, which could occur by the end of this year.

The project has received approvals to introduce fuel gas to the first and second gas turbine generator, as well as to supply liquid nitrogen to the air separation unit, US FERC said in several recent fillings.

This means the project had started commissioning activities and one of the next major steps would be to introduce feed gas to the liquefaction units.

A report by Platts also said that Venture Global LNG’s chief commercial officer Tom Earl revealed last week during the Gastech conference in Dubai the project would begin production “within months.”

The Calcasieu Pass project will produce about 10 mtpa of LNG from 18 modular units configured in 9 blocks.

Venture Global gets Calcasieu Pass modular trains from Baker Hughes’ manufacturing facility in Italy.

The firm also said in a filing to FERC in March that it could start first exports from the LNG facility by the end of this year, with full operations planned in mid-2022.

Some reports also suggested the firm had issued a tender for cargoes from Calcasieu Pass for delivery starting later this year.

Once operational, the Calcasieu Pass project would become the seventh large LNG export facility in the US.

Besides this project, Venture Global recently said it had started works to prepare the construction site for its planned Plaquemines LNG project in Louisiana.

Plaquemines LNG would deploy Venture Global’s liquefaction trains 19 through 36, identical to the 18 trains currently being delivered and installed at Calcasieu Pass.

Most Popular

YPF, Indian firms ink Argentina LNG deal

According to a statement by YPF, the firm signed the MoU with GAIL, Oil India, and ONGC Videsh...

Trump lifts pause on non-FTA LNG export approvals

Trump issued the executive order, which was widely expected, just hours after officially taking over his second four-year term...

Golar’s FLNG gets first gas from GTA field

According to a statement by Golar, the "key" milestone took place on January 18. Golar said full commissioning of the...

More News Like This

Venture Global LNG slashes IPO price range

Venture Global initially planned to offer 50 million of its Class A common stock priced between $40 and $46...

Trump lifts pause on non-FTA LNG export approvals

Trump issued the executive order, which was widely expected, just hours after officially taking over his second four-year term...

Second Plaquemines LNG cargo arrives in Germany

Venture Global’s 174,000-cbm newbuild carrier, Venture Gator, was on Monday anchored in the North Sea, offshore Wilhelmshaven and Brunsbüttel,...

Third Plaquemines LNG cargo heads to Europe

The 2021-built 174,000-cbm, Isabella, was on Friday located in the North Atlantic Ocean, offshore Bahamas, after picking up a...