Venture Global nears first LNG cargo from Calcasieu Pass

Venture Global LNG’s Calcasieu Pass export project in Louisiana continues to progress towards first LNG production, which could occur by the end of this year.

The project has received approvals to introduce fuel gas to the first and second gas turbine generator, as well as to supply liquid nitrogen to the air separation unit, US FERC said in several recent fillings.

This means the project had started commissioning activities and one of the next major steps would be to introduce feed gas to the liquefaction units.

A report by Platts also said that Venture Global LNG’s chief commercial officer Tom Earl revealed last week during the Gastech conference in Dubai the project would begin production “within months.”

The Calcasieu Pass project will produce about 10 mtpa of LNG from 18 modular units configured in 9 blocks.

Venture Global gets Calcasieu Pass modular trains from Baker Hughes’ manufacturing facility in Italy.

The firm also said in a filing to FERC in March that it could start first exports from the LNG facility by the end of this year, with full operations planned in mid-2022.

Some reports also suggested the firm had issued a tender for cargoes from Calcasieu Pass for delivery starting later this year.

Once operational, the Calcasieu Pass project would become the seventh large LNG export facility in the US.

Besides this project, Venture Global recently said it had started works to prepare the construction site for its planned Plaquemines LNG project in Louisiana.

Plaquemines LNG would deploy Venture Global’s liquefaction trains 19 through 36, identical to the 18 trains currently being delivered and installed at Calcasieu Pass.

Most Popular

GTT opens Qatar office

French LNG containment giant GTT has opened a new office in Doha, Qatar's capital and economic hub. GTT’s chairman Philippe...

Eni’s FLNG launched in China

According to separate statements by Eni and WNE, the launching of the hull took place on Saturday. In Congo's Lingala...

Venture Global’s Plaquemines LNG to introduce hazardous fluids to first block

The regulator said on Thursday it had granted Venture Global Plaquemines LNG to commission and introduce hazardous fluids to...

More News Like This

Venture Global’s Plaquemines LNG to introduce hazardous fluids to first block

The regulator said on Thursday it had granted Venture Global Plaquemines LNG to commission and introduce hazardous fluids to...

Venture Global’s vessel arrives at Plaquemines LNG plant

The 174,000-cbm LNG carrier was on Tuesday located at the LNG plant along the Mississippi River, according to its...

BP, Venture Global to supply LNG to Bulgargaz in January and February

Bulgargaz previously sought two LNG cargoes for delivery during January and February 2025. The company recently announced that 19 international...

Venture Global nears launch of Plaquemines LNG production

According to a FERC filing, Plaquemines LNG has now fulfilled the environmental conditions which were necessary prior to the...