LNG Canada pipeline more than 50 percent complete

TC Energy’s Coastal GasLink pipeline project, which will supply natural gas to the Shell-led LNG Canada plant, has surpassed the 50 percent completion mark.

Coastal GasLink said in an update the overall progress had reached 53.1 percent, as it continues to work towards its target completion date in 2023.

“This means 100 percent of the 670-km route is cleared, and grading is more than 60 percent complete. We’ve also safely installed more than 200 kilometers of pipe,” it said.

The pipeline has a price tag of more than C$6.6 billion ($5.32 billion). However, Coastal GasLink and LNG Canada previously said they were in commercial discussions regarding the cost and schedule for the project.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat, British Columbia.

LNG Canada pipeline more than 50 percent complete
Image: LNG Canada

This milestone announcement comes just weeks after LNG Canada said it had surpassed the 50 percent completion mark.

LNG Canada has also recently placed the 300+ tonne main cryogenic heat exchanger (MCHE) and two precooler units.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation but also South Korea’s Kogas.

LNG Canada expects the first LNG shipment from the first phase of the plant, which includes two trains with a capacity of 14 mtpa, in the middle of the decade.

Most Popular

Petrovietnam units plan new LNG-to-power project

PV Power and PV Gas, units of state-owned Petrovietnam, signed cooperation agreements to secure gas supplies for power plants in southwestern Vietnam and explore developing an integrated liquefied natural gas (LNG) project in the northern port city of Hai Phong.

Glenfarne’s Texas LNG seeks DOE extension

US energy firm Glenfarne is seeking an extension from the US Department of Energy to extend the non-FTA export start deadline for its planned 4 mtpa Texas LNG export terminal in the port of Brownsville.

Colombia’s Ecopetrol ditches LNG import tenders

Colombia’s state-owned energy firm Ecopetrol has rejected five-year liquefied natural gas (LNG) supply offers, saying that the minimum commercial conditions were not met.

More News Like This

Canada backs Fort Simpson LNG power plant

The government of Canada is backing the construction of NTPC's new power plant in Fort Simpson that will primarily generate power using liquefied natural gas (LNG).

Tecnicas Reunidas scores LNG Canada pipeline gig

Shell-led LNG Canada has awarded a contract to Spanish engineering and construction firm Tecnicas Reunidas to provide EPCM services for the second phase of the Coastal GasLink pipeline in British Columbia, on Canada’s west coast.

First Nations invest in LNG Canada pipeline

Canada's TC Energy, operator of the LNG Canada pipeline, said it had closed an agreement with FN CGL Pipeline, an Indigenous-led investment entity representing five First Nations along the Coastal GasLink corridor.

Shell, partners take FID on LNG Canada Phase 2

UK-based LNG giant Shell and its LNG Canada partners have made a final investment decision on the project's second phase, which will double production capacity at the facility in Kitimat, British Columbia.