Saipem does not expect Mozambique LNG work to resume this year

Italian contractor Saipem does not expect work on the TotalEnergies-led Mozambique LNG project to resume in 2022, according to its chief operating officer Alessandro Puliti.

France’s TotalEnergies declared force majeure on the $20 billion LNG project in April last year following new attacks, and withdrew all personnel from the site.

In February this year, TotalEnergies said it would not restart work on the project until the civil population comes back to the Cabo Delgado province where the Afungi site is located.

The project’s EPC contractor is CCS JV, a venture between Saipem, McDermott, and Chiyoda.

Saipem previously said that the firm had expected work to resume on the project this year.

However, the firm now does not see resumption of work prior to 2023. Saipem also said that the EPC contract would have to be amended due to surging costs.

“Our current costs are covered in a fully reimbursable scheme from the client and we do not expect any restart of operation within 2022,” Puliti told analysts on Wednesday during Saipem’s first-half results call.

“Completely different world”

CEO Francesco Caio said that compared to 2019 when the CCS JV won the Mozambique LNG contract, “we are in a completely different world today.”

This is due the Covid pandemic and “because of the inflation of the raw materials that we have been experiencing starting at the end of 2021, even before the beginning of the Ukrainian crisis,” he said.

He said that the costs and terms for the Mozambique contract would have to be changed, “because what was agreed back and the beginning of the project is clearly no longer sustainable.”

“So, their full restart of the project will be definitely on different basis, a renegotiated basis with the client,” Caio said.

Prior to this, TotalEnergies had expected to launch the Mozambique LNG project in 2024.

The project includes the development of offshore gas fields in Mozambique’s Area 1 and a 12.8 mtpa liquefaction plant at the Afungi complex.

Besides TotalEnergies, other partners in the project are Japan’s Mitsui, Mozambique’s ENH, Thailand’s PTT, and Indian firms ONGC, Bharat Petroleum, and Oil India.

- Advertisements -

Most Popular

QatarEnergy seals $6 billion deal with Chinese shipbuilder for 18 giant LNG carriers

State-owned LNG giant QatarEnergy has signed a major shipbuilding deal worth $6 billion with China State Shipbuilding Corp for...

TotalEnergies CEO: Mozambique LNG restart is not a matter of costs

French energy giant TotalEnergies had "good" discussions with Mozambique LNG contractors and they agreed not to inflate the costs...

NFE says ‘minor mechanical issue’ will not affect Altamira LNG launch

US LNG player New Fortress Energy said that "a minor technical issue" which took place last week on one...

More News Like This

TotalEnergies CEO: Mozambique LNG restart is not a matter of costs

French energy giant TotalEnergies had "good" discussions with Mozambique LNG contractors and they agreed not to inflate the costs...

TotalEnergies reports lower Q1 LNG earnings, sales

France’s TotalEnergies said on Friday that the company’s integrated LNG business logged a decline in its adjusted net operating...

Oman LNG delivered 173 cargoes last year, revenue reached $4.9 billion

State-owned Oman LNG delivered 173 cargoes of liquefied natural gas from its Qalhat complex in 2023, down by three...

Mitsui: no decision on Adnoc’s LNG project

Japan's trading house Mitsui & Co said nothing has been decided on an LNG project in the United Arab...