Cheniere’s third Sabine Pass LNG jetty almost complete

US LNG exporting giant Cheniere and compatriot Bechtel have almost completed the third jetty project at the six-train 30 mtpa Sabine Pass LNG facility in Louisiana.

According to the latest construction update filed with FERC, the third jetty project was 99.1 percent complete as of August this year, compared to 96.4 percent in July.

“Currently, engineering, procurement, and subcontracts are 100 percent complete against the plan of 100 percent, and construction is 97.5 percent complete against the plan of 97.2 percent,” Cheniere said in the update.

Cheniere started commissioning of the third jetty’s LNG loading arms in August.

“Final preparations for the introduction of hydrocarbons and cooldown commenced and are on track to finish in early September,” it said.

According to Cheniere, it plans to complete commissioning of LNG transfer arms during September.

It appears that the third jetty has already welcomed at least one LNG tanker.

The 174,000-cbm LNG carriers, Aristarchos, owned by Capital Product Partners and chartered by Cheniere, visited the new berth earlier this month, its AIS data shows.

VesselsValue data shows that the vessel was on Friday located at Elengy’s Montoir-de-Bretagne LNG import terminal in France.

Boosting capacity

Cheniere and compatriot Bechtel are adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

Moreover, it will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at Cheniere’s plant by 180 per year.

The operator of the Sabine Pass and Corpus Christi terminals recently revealed plans to increase the company’s liquefaction capacity to about 90 mtpa as part of its “20/20 Vision” long-term capital allocation plan.

Also, Cheniere recently took a final investment decision on Stage 3 expansion at its Corpus Christi LNG export plant in Texas.

The expansion will add about 10 mtpa to the three-train 15 mtpa Corpus Christi plant.

Most Popular

Venture Global’s CP2 LNG to start mobilization and site preparation

Venture Global LNG's CP2 LNG has received approval from the US FERC to start mobilization and other limited activities for the LNG project in Louisiana.

Cheniere kicks off Sabine Pass LNG maintenance

US LNG exporting giant Cheniere has started planned maintenance at its Sabine Pass LNG export facility in Louisiana.

BP seals LNG SPA with India’s Torrent Power

A unit of UK-based energy giant BP has signed a long-term liquefied natural gas (LNG) supply deal with India's Torrent Power.

More News Like This

Port of Corpus Christi completes ship channel expansion

The US Port of Corpus Christi in Texas has completed the $625 million ship channel improvement project.

Cheniere kicks off Sabine Pass LNG maintenance

US LNG exporting giant Cheniere has started planned maintenance at its Sabine Pass LNG export facility in Louisiana.

Cheniere to introduce feed gas to second Corpus Christi expansion train

US LNG exporter Cheniere is nearing the introduction of feed gas to the second train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere, Canadian Natural Resources pen gas supply deal

US LNG exporter Cheniere has signed a long-term deal with Canadian Natural Resources under which the latter will supply natural gas to a unit of Cheniere.