Cheniere’s third Sabine Pass LNG jetty almost complete

US LNG exporting giant Cheniere and compatriot Bechtel have almost completed the third jetty project at the six-train 30 mtpa Sabine Pass LNG facility in Louisiana.

According to the latest construction update filed with FERC, the third jetty project was 99.1 percent complete as of August this year, compared to 96.4 percent in July.

“Currently, engineering, procurement, and subcontracts are 100 percent complete against the plan of 100 percent, and construction is 97.5 percent complete against the plan of 97.2 percent,” Cheniere said in the update.

Cheniere started commissioning of the third jetty’s LNG loading arms in August.

“Final preparations for the introduction of hydrocarbons and cooldown commenced and are on track to finish in early September,” it said.

According to Cheniere, it plans to complete commissioning of LNG transfer arms during September.

It appears that the third jetty has already welcomed at least one LNG tanker.

The 174,000-cbm LNG carriers, Aristarchos, owned by Capital Product Partners and chartered by Cheniere, visited the new berth earlier this month, its AIS data shows.

VesselsValue data shows that the vessel was on Friday located at Elengy’s Montoir-de-Bretagne LNG import terminal in France.

Boosting capacity

Cheniere and compatriot Bechtel are adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

Moreover, it will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at Cheniere’s plant by 180 per year.

The operator of the Sabine Pass and Corpus Christi terminals recently revealed plans to increase the company’s liquefaction capacity to about 90 mtpa as part of its “20/20 Vision” long-term capital allocation plan.

Also, Cheniere recently took a final investment decision on Stage 3 expansion at its Corpus Christi LNG export plant in Texas.

The expansion will add about 10 mtpa to the three-train 15 mtpa Corpus Christi plant.

Most Popular

South Korea’s Samsung Heavy secures order for LNG carrier quartet

South Korean shipbuilding giant Samsung Heavy Industries has secured an order to build four liquefied natural gas (LNG) carriers for approximately $1.05 billion.

TotalEnergies, GS Energy pen long-term LNG SPA

French energy giant TotalEnergies has entered into a long-term agreement with South Korea’s GS Energy to supply the latter with liquefied natural gas (LNG).

TotalEnergies and T&T join forces on LNG-to-power project in Vietnam

French energy giant TotalEnergies and Vietnamese conglomerate T&T have signed a memorandum of understanding to jointly develop the 1,500 MW Long Son LNG-to-power project in Vietnam.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project more than 50 percent complete

Cheniere's Corpus Christi Midscale Trains 8 and 9 project in Texas is more than 50 percent complete, according to the latest construction update.

Equinor takes first LNG cargo from Cheniere

Norwegian energy firm Equinor has taken delivery of its first liquefied natural gas (LNG) cargo under long-term supply agreements with US LNG exporting giant Cheniere.

Cheniere completes CCL Stage 3 project

US LNG exporter Cheniere has completed the Corpus Christi Liquefaction Stage 3 expansion project in Texas. In addition, Cheniere has also exported its 5,000th LNG cargo since 2016.

Germany’s BASF gets first LNG cargo under Cheniere contract

German chemicals giant BASF has received its first liquefied natural gas (LNG) cargo under a long-term contract with US LNG exporter Cheniere.