Cheniere’s third Sabine Pass LNG jetty almost complete

US LNG exporting giant Cheniere and compatriot Bechtel have almost completed the third jetty project at the six-train 30 mtpa Sabine Pass LNG facility in Louisiana.

According to the latest construction update filed with FERC, the third jetty project was 99.1 percent complete as of August this year, compared to 96.4 percent in July.

“Currently, engineering, procurement, and subcontracts are 100 percent complete against the plan of 100 percent, and construction is 97.5 percent complete against the plan of 97.2 percent,” Cheniere said in the update.

Cheniere started commissioning of the third jetty’s LNG loading arms in August.

“Final preparations for the introduction of hydrocarbons and cooldown commenced and are on track to finish in early September,” it said.

According to Cheniere, it plans to complete commissioning of LNG transfer arms during September.

It appears that the third jetty has already welcomed at least one LNG tanker.

The 174,000-cbm LNG carriers, Aristarchos, owned by Capital Product Partners and chartered by Cheniere, visited the new berth earlier this month, its AIS data shows.

VesselsValue data shows that the vessel was on Friday located at Elengy’s Montoir-de-Bretagne LNG import terminal in France.

Boosting capacity

Cheniere and compatriot Bechtel are adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

Moreover, it will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at Cheniere’s plant by 180 per year.

The operator of the Sabine Pass and Corpus Christi terminals recently revealed plans to increase the company’s liquefaction capacity to about 90 mtpa as part of its “20/20 Vision” long-term capital allocation plan.

Also, Cheniere recently took a final investment decision on Stage 3 expansion at its Corpus Christi LNG export plant in Texas.

The expansion will add about 10 mtpa to the three-train 15 mtpa Corpus Christi plant.

Most Popular

CoolCo seeks long-term employment for two LNG carriers

In August, Coolco said it plans to employ its first newbuild LNG vessel, Kool Tiger, on a shorter deal...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

Japan’s K Line on track with LNG fleet growth plans

According to K Line's latest financial report, the firm had 46 LNG carriers in its fleet as of the...

More News Like This

Corpus Christi LNG expansion project 73.2 percent complete

Cheniere’s Corpus Christi plant currently liquefies natural gas at three operational trains, each with a capacity of about 5...

Cheniere sets methane emissions target for its LNG terminals

US LNG exporting giant Cheniere said it had set a voluntary, measurement-informed scope 1 annual methane intensity target for...

Cheniere CEO: Corpus Christi expansion project to get first gas in coming weeks

Cheniere’s Corpus Christi plant in Texas currently liquefies natural gas at three operational trains, each with a capacity of...

Cheniere boosts LNG shipments in January-September

The owner of the Sabine Pass and Corpus Christi LNG export terminals said on Thursday that its revenue reached...