Cheniere to start commissioning third jetty at Sabine Pass LNG terminal

Cheniere is preparing to start commissioning activities of the third jetty project at its six-train 30 mtpa Sabine Pass LNG facility in Louisiana.

The company’s unit Sabine Pass LNG has submitted compliance documentation with the US FERC for the introduction of hydrocarbons associated with the third berth project.

“Sabine Pass is requesting authorization at the earliest date possible, but no later than August 26, 2022, in order to remain on schedule,” the firm said in a filling.

“Prior to commissioning, Sabine Pass shall file detailed plans and procedures for: testing the integrity of onsite mechanical installation; functional tests; introduction of hazardous fluids; operational tests; and placing the equipment into service,” it said.

According to the latest construction update filed with FERC, the third jetty project was 96.4 percent complete as of July this year.

Cheniere and compatriot engineer Bechtel are adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year.

Cheniere said earlier this year that operations of the jetty could start by the end of 2022.

Besides the Sabine Pass plant, Cheniere recently took a final investment decision on Stage 3 expansion at its Corpus Christi LNG export plant in Texas.

The expansion will add about 10 mtpa to the three-train 15 mtpa Corpus Christi plant.

In addition, Cheniere’s CEO Jack Fusco recently said the company was working to add over 30 million tonnes of capacity at its Sabine Pass and Corpus Christi plants.

Most Popular

Cheniere to start site preparation for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is seeking approval from the US FERC to start site preparation activities for two more midscale trains at its Corpus Christi LNG plant in Texas.

Amigo LNG, Sahara seal 20-year SPA

Amigo LNG, a unit of LNG Alliance, has signed a 20-year sales and purchase agreement with Sahara Group to supply the latter with liquefied natural gas from its planned 7.8 mtpa LNG export plant in Mexico.

LNG shipping rates continue to decrease

Spot LNG freight shipping rates in both basins continued to decrease this week, while European prices increased compared to last week.

More News Like This

Cheniere to start site preparation for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is seeking approval from the US FERC to start site preparation activities for two more midscale trains at its Corpus Christi LNG plant in Texas.

Port of Corpus Christi says Q1 LNG volumes up 12.3 percent

The US Port of Corpus Christi in Texas reported a 12.3 percent year-on-year increase in its liquefied natural gas (LNG) volumes in the first quarter of this year.

Cheniere progresses commissioning of second Corpus Christi expansion train

US LNG exporting giant Cheniere is moving forward with commissioning activities at the second train of the Corpus Christi Stage 3 expansion project in Texas following the substantial completion of the first unit.

Corpus Christi LNG expansion project 80 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 80 percent complete.