Freeport LNG gets OK to return second jetty to service

Freeport LNG, the operator of the three-train 15 mtpa liquefaction plant in Texas, received approval from the US FERC to place back into service its second jetty.

In October, Freeport received approval from the FERC to start commissioning its second jetty.

The commissioning and cooldown included the Loop 2 transfer piping, Dock, 2 and the recirculation piping.

In order to continue Freeport’s sequential plan to return the LNG export facility to full commercial operations, Freeport requested authorization from the FERC last week to place Loop 2 and Dock 2 back into service.

The regulator granted Freeport’s request to return to service Phase II facilities which includes LNG Loop 2 and Dock 2 for ship loading, according to a filling dated November 22.

“This approval is based on a review of the written request filed on November 17, 2023, previous submittals and supplements filed in response to certain actions taken to address the root and contributing causes identified as a result of the June 8, 2022 incident as well as satisfactory progression of cooldown activities, including remedial actions taken during cooldown,” the FERC said.

The regulator said that this does not grant Freeport authorization to commission or place LNG Tank 3 back into service.

Also, the FERC noted that Freeport must also comply with any applicable PHMSA and US Coast Guard requirements.

In February this year, the LNG terminal operator shipped the first cargo from its LNG export plant in Texas since the shutdown in June 2022.

Freeport received approvals from both FERC and PHMSA during the first quarter to restart Phase I operations.

These consist of three trains, two LNG storage tanks (tanks 1 and 2), and a single LNG jetty (dock 1).

Most Popular

Venture Global withdraws Delta LNG application

US LNG exporter Venture Global LNG is withdrawing its FERC application for the proposed 24.4 mtpa Delta LNG export facility in Louisiana. Instead, Venture Global will focus on expanding its Plaquemines LNG export facility in Louisiana.

Delfin seeks new DOE extension, eyes FID on first FLNG in August

Delfin Midstream, the US developer of a floating LNG export project offshore Louisiana, is seeking an additional extension from the US Department of Energy. The company is looking to make a final investment decision on the first FLNG in August.

Tortue LNG cargo heads to Europe

UK-based energy giant BP has shipped the third LNG cargo produced at the Greater Tortue Ahmeyim FLNG project, located offshore Mauritania and Senegal, to Europe, according to shipping data.

More News Like This

Woodside’s Louisiana LNG gets FERC extension

Woodside has secured an additional eight-month extension from the US FERC to complete and put into service its Louisiana LNG export facility.

Cheniere aims to start construction on Sabine Pass LNG expansion in late 2026

US LNG exporting giant Cheniere aims to start construction on the proposed expansion project at its Sabine Pass LNG export facility in Louisiana in late 2026.

Venture Global withdraws Delta LNG application

US LNG exporter Venture Global LNG is withdrawing its FERC application for the proposed 24.4 mtpa Delta LNG export facility in Louisiana. Instead, Venture Global will focus on expanding its Plaquemines LNG export facility in Louisiana.

Venture Global’s Plaquemines LNG to commission third jetty

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce hazardous fluids to the third jetty at its Plaquemines LNG export plant in Louisiana.