Cheniere’s Corpus Christi LNG expansion project almost 53 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 53 percent complete, and the US LNG exporting giant is working to start production at the first train later this year.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and compatriot Bechtel officially started construction on the project in October the same year.

The project was 51.4 percent complete in December last year.

It includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the January construction report filed with the US FERC last week that overall project completion for the Stage 3 project is 52.7 percent.

Stage 3 engineering and procurement are 86 percent and 72.9 percent complete, respectively, while subcontract and direct hire construction work are 69.5 percent and 12.3 percent complete, respectively.

Cheniere’s Corpus Christi LNG expansion project almost 53 complete
Image: Cheniere

First train work continues to progress

During January, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work and mobilization of temporary facilities, equipment.

Piling activities continued in trains 5 and 6. Concrete work in train 1 is “significantly complete” and underway in train 2, train 3, and OSBL, the company said.

Moreover, structural steel in train 1 is over halfway complete and has started in train 2 and OSBL, it said.

Underground piping is progressing in train 1, 2, 3, and OSBL and has started in train 4, while aboveground piping is progressing in train 1, train 2, and OSBL West.

CCL said equipment setting is ongoing in Train 1 and Train 2.

Cheniere’s Corpus Christi LNG expansion project almost 53 complete
Train 2 regen gas compressor set

First LNG production by end of 2024

Cheniere initially said that LNG deliveries from the expansion project were expected to begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

The company also confirmed in its 2023 report that it that it expects to achieve first LNG production from the first train at the end of 2024.

Besides this expansion, Cheniere plans to build two more liquefaction trains as part of the third expansion phase at the Corpus Christi plant.

The firm’s results show that it aims to take a final investment decision on CCL midscale trains 8 and 9 in 2025, subject to regulatory approvals.

In addition, Cheniere also aims to build two new liquefaction trains as part of the Sabine Pass Stage 5 expansion project to add up to 20 mtpa of capacity to the giant facility.

Cheniere plans to take FID on this project in 2026, subject to regulatory approvals.

Most Popular

Shell adds another LNG carrier to its fleet

A unit of UK-based LNG giant Shell has added another chartered liquefied natural gas carrier to its fleet.

Hanwha Engine completes first X-DF engine with VCR tech

South Korea's Hanwha Engine, a subsidiary of Hanwha, has completed what it claims is the world's first WinGD X-DF engine equipped with VCR (variable compression ratio) technology for LNG carriers.

Chevron, China’s ENN seal second LNG SPA

US energy giant Chevron has signed a second LNG sales and purchase agreement with Chinese independent gas distributor ENN.

More News Like This

Trafigura, Kogas seal long-term US LNG supply deal

LNG trader Trafigura has signed a long-term deal to supply US LNG to South Korean importer Kogas.

Cheniere nears first LNG at third Corpus Christi expansion train

US LNG exporter Cheniere is nearing the start of LNG production at the third train of the Corpus Christi Stage 3 expansion project in Texas as part of the commissioning phase.

Cheniere, Jera seal long-term LNG SPA

US LNG exporter Cheniere has signed a long-term LNG sale and purchase agreement with Japan's Jera.

Cheniere completes second train at Corpus Christi LNG expansion project

US LNG exporting giant Cheniere has achieved substantial completion of the second liquefaction train at the Corpus Christi Stage 3 expansion project in Texas.