ExxonMobil says Golden Pass plant on track to deliver first LNG in H1 2025

Energy giants QatarEnergy and ExxonMobil are still expecting to start LNG production at their Golden Pass LNG export terminal on the US Gulf Coast near Sabine Pass, Texas, in the first half of 2025.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

“Train 1 mechanical completion is expected at the end of 2024 with first LNG in the first half of 2025,” Darren Woods, chairman and CEO of ExxonMobil, said during the fourth-quarter earnings call on February 2.

Woods did not provide further information.

He confirmed an announcement in December by ExxonMobil’s senior VP and CFO, Kathryn Mikellss, during the company’s corporate plan that first LNG is expected in first half of 2025.

The partners previously expected to complete the first Golden Pass train in the first quarter of 2024.

The US FERC said in an inspection report in January this year that the anticipated in-service timing for the first Golden Pass train is the second half of 2024,with train 2 and 3 following after.

According to the report, the anticipated in-service timing for the pipeline expansion project is expected “sometime prior to the second half of 2024”.

Construction update

Golden Pass LNG Terminal and Golden Pass Pipeline also recently filed the latest construction report with the FERC.

The report said that Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas and flare wall modifications, continued piping and vessels insulation activities, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins in Trains 2 and 3, and progressed brownfield tie-ins and LNG tank tops modifications scope.

Golden Pass also progressed cable tray installations and cable pulling activities and continued pipe pneumatic / hydrostatic testing program.

As per the pipeline expansion project, Golden Pass continued civil activities and concrete foundation pours at milepost MP33 and MP69 compressor stations and also continued pipe fabrication and installation at these stations.

It also continued construction activities of the Sabine Spur, Natural Gas Pipeline (NGPL)
Interconnect improvements, and associated facilities.

Most Popular

Cheniere produces first LNG cargo at Corpus Christi expansion project

US LNG exporting giant Cheniere has produced the first cargo at the Corpus Christi Stage 3 expansion project in Texas.

Centrica seals LNG supply deal with Petrobras

UK-based energy firm Centrica has signed a 15-year LNG supply deal with Brazil’s state-owned energy firm Petrobras.

Japan’s Japex boosts LNG sales

Japan Petroleum Exploration (Japex) boosted its sales of liquefied natural gas (LNG) in the April-December period last year.

More News Like This

Hanwha Ocean delivers 200th LNG carrier

South Korea's Hanwha Ocean has delivered its 200th liquefied natural gas (LNG) carrier.

Sicim bags Rovuma LNG gig

Italy's Sicim has secured a contract from Subsea 7 for the ExxonMobil-led Rovuma LNG project in Mozambique.

Construction advances on Golden Pass LNG terminal

Energy giants QatarEnergy and ExxonMobil and their contractors continue to move forward with the construction work on the Golden Pass LNG export facility in Texas.

TotalEnergies CEO says partners working hard on Papua LNG

TotalEnergies has a 37.55 percent operating stake in the Papua LNG project, ExxonMobil has 37.04 percent, Santos owns a...