ExxonMobil says Golden Pass plant on track to deliver first LNG in H1 2025

Energy giants QatarEnergy and ExxonMobil are still expecting to start LNG production at their Golden Pass LNG export terminal on the US Gulf Coast near Sabine Pass, Texas, in the first half of 2025.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

“Train 1 mechanical completion is expected at the end of 2024 with first LNG in the first half of 2025,” Darren Woods, chairman and CEO of ExxonMobil, said during the fourth-quarter earnings call on February 2.

Woods did not provide further information.

He confirmed an announcement in December by ExxonMobil’s senior VP and CFO, Kathryn Mikellss, during the company’s corporate plan that first LNG is expected in first half of 2025.

The partners previously expected to complete the first Golden Pass train in the first quarter of 2024.

The US FERC said in an inspection report in January this year that the anticipated in-service timing for the first Golden Pass train is the second half of 2024,with train 2 and 3 following after.

According to the report, the anticipated in-service timing for the pipeline expansion project is expected “sometime prior to the second half of 2024”.

Construction update

Golden Pass LNG Terminal and Golden Pass Pipeline also recently filed the latest construction report with the FERC.

The report said that Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas and flare wall modifications, continued piping and vessels insulation activities, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins in Trains 2 and 3, and progressed brownfield tie-ins and LNG tank tops modifications scope.

Golden Pass also progressed cable tray installations and cable pulling activities and continued pipe pneumatic / hydrostatic testing program.

As per the pipeline expansion project, Golden Pass continued civil activities and concrete foundation pours at milepost MP33 and MP69 compressor stations and also continued pipe fabrication and installation at these stations.

It also continued construction activities of the Sabine Spur, Natural Gas Pipeline (NGPL)
Interconnect improvements, and associated facilities.

Most Popular

Venture Global seals new deals to support expansion of its power network

US LNG exporter Venture Global has entered into power and grid frame agreements with GE Vernova and Baker Hughes for up to 16 new, 720 MW power island units and associated power transformer equipment, supporting the continued expansion of its existing behind-the-meter, industrial power network that is not reliant on the grid.

Venture Global gets approval to place first Plaquemines LNG phase in service

Venture Global’s Plaquemines LNG has secured approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

Hanwha Ocean, Posco plan to build LNG carrier with high-manganese steel tanks

South Korean shipbuilder Hanwha Ocean and steel producer Posco plan to build a liquefied natural gas (LNG) carrier equipped with high-manganese steel cargo tanks.

More News Like This

MISC names QatarEnergy LNG carrier

South Korea's Samsung Heavy Industries hosted a naming ceremony for a liquefied natural gas (LNG) carrier it built for Malaysia's MISC and state-owned LNG giant QatarEnergy.

Edison says QatarEnergy extends force majeure until early December

Italian energy firm Edison, a unit of EDF, said it received a new force majeure notification from state-owned LNG giant QatarEnergy, affecting supplies scheduled for delivery at the Adriatic LNG terminal in Italy until the beginning of December.

ExxonMobil’s Rovuma LNG seeks contractor for land transportation services

US energy giant ExxonMobil and its partners in the planned Rovuma LNG project in Mozambique have invited companies to submit expressions of interest to provide land transportation services.

ExxonMobil’s PNG LNG hits production milestone

The ExxonMobil-operated PNG LNG project in Papua New Guinea has reached a new milestone, producing more than 100 million tons of liquefied natural gas (LNG) since operations began in 2014.