LNG Canada pipeline almost 58 percent complete

TC Energy’s Coastal GasLink pipeline project, which will supply natural gas to the Shell-led LNG Canada plant, has almost reached the 58 percent completion mark.

Coastal GasLink said in an update the overall progress had reached 57.7 percent, as it continues to work towards its target completion date in 2023.

It recently reached the 50 percent completion mark on the 670 km long pipeline.

“On December 3, we celebrated our most recent milestone — the fabrication and delivery of all the pipeline assemblies to our storage facilities,” Coastal GasLink said.

“In total we shipped thirty-one 48-inch block valves along with associated assembly piping, 259 3D elbows, and 87 test heads and caps. This equated to over 100,000 factored weld-inches completed, or over 250 truckloads of material assembled,” it said.

The pipeline has a price tag of more than C$6.6 billion ($5.11 billion). However, Coastal GasLink and LNG Canada previously said they were in commercial discussions regarding the cost and schedule for the project.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat, British Columbia.

LNG Canada also recently passed the 50 percent completion mark and installed the main absorber column.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation but also South Korea’s Kogas.

LNG Canada expects the first LNG shipment from the first phase of the plant, which includes two trains with a capacity of 14 mtpa, in the middle of the decade.

- Advertisements -

Most Popular

Golden Pass LNG to ramp up construction activities after Zachry deal

QatarEnergy and ExxonMobil will ramp up construction activities at the Golden Pass LNG export terminal in Texas after a...

Hudong-Zhonghua confirms TotalEnergies order for LNG bunkering vessel

China’s Hudong-Zhonghua said it had secured an order to build one 18,600-cbm LNG bunkering vessel for French energy giant...

India was top destination for US LNG cargoes in May

India was the top destination for US liquefied natural gas cargoes in May, as Asia overtook Europe as the...

More News Like This

Fluor and JGC move one step closer to completion of LNG Canada’s first train

US engineer Fluor announced completion of the final weld on the first production train at the Shell-led LNG Canada...

Malaysia’s Petronas adds new vessels to its fleet as LNG Canada launch nears

Malaysian energy giant Petronas has added three new liquefied natural gas (LNG) carriers to its fleet as it prepares...

Shell CEO: LNG Canada to start commissioning later this year

Shell’s LNG Canada terminal is more than 90 percent complete and the project is preparing to launch commissioning activities...

LNG Canada CEO: start-up activities will take more than a year to complete

Shell's LNG Canada project is now preparing to launch start-up activities next year and this program will take more...