LNG Canada pipeline more than 50 percent complete

TC Energy’s Coastal GasLink pipeline project, which will supply natural gas to the Shell-led LNG Canada plant, has surpassed the 50 percent completion mark.

Coastal GasLink said in an update the overall progress had reached 53.1 percent, as it continues to work towards its target completion date in 2023.

“This means 100 percent of the 670-km route is cleared, and grading is more than 60 percent complete. We’ve also safely installed more than 200 kilometers of pipe,” it said.

The pipeline has a price tag of more than C$6.6 billion ($5.32 billion). However, Coastal GasLink and LNG Canada previously said they were in commercial discussions regarding the cost and schedule for the project.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat, British Columbia.

LNG Canada pipeline more than 50 percent complete
Image: LNG Canada

This milestone announcement comes just weeks after LNG Canada said it had surpassed the 50 percent completion mark.

LNG Canada has also recently placed the 300+ tonne main cryogenic heat exchanger (MCHE) and two precooler units.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation but also South Korea’s Kogas.

LNG Canada expects the first LNG shipment from the first phase of the plant, which includes two trains with a capacity of 14 mtpa, in the middle of the decade.

- Advertisements -

Most Popular

Delfin plans to take FID on first floating LNG producer in Q2

Delfin Midstream, the developer of a floating LNG export project in the Gulf of Mexico, is expecting to take...

ExxonMobil working on larger Rovuma LNG export project in Mozambique

US energy giant ExxonMobil has boosted the capacity of the planned Rovuma LNG onshore terminal in Mozambique and is...

Mexico Pacific seals another LNG supply deal with Shell

A unit of LNG giant Shell has signed another long-term deal to buy liquefied natural gas from Mexico Pacific,...

More News Like This

EnerMech clinches Canadian LNG gig

A unit of EnerMech has secured a contract to deliver its mechanical pre-commissioning and commissioning services to a large...

China’s COOEC wraps up LNG Canada module job

China Offshore Oil Engineering (COOEC), a unit of CNOOC, has delivered the last two modules it built for the...

LNG Canada’s new tug berth to be completed in early 2024

A new tug berth being built for the Shell-led LNG Canada export project will be ready in early 2024...

TC Energy says LNG Canada pipeline 84 percent complete, evaluates second phase

TC Energy said that its Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada export...