LNG Canada pipeline more than 50 percent complete

TC Energy’s Coastal GasLink pipeline project, which will supply natural gas to the Shell-led LNG Canada plant, has surpassed the 50 percent completion mark.

Coastal GasLink said in an update the overall progress had reached 53.1 percent, as it continues to work towards its target completion date in 2023.

“This means 100 percent of the 670-km route is cleared, and grading is more than 60 percent complete. We’ve also safely installed more than 200 kilometers of pipe,” it said.

The pipeline has a price tag of more than C$6.6 billion ($5.32 billion). However, Coastal GasLink and LNG Canada previously said they were in commercial discussions regarding the cost and schedule for the project.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat, British Columbia.

LNG Canada pipeline more than 50 percent complete
Image: LNG Canada

This milestone announcement comes just weeks after LNG Canada said it had surpassed the 50 percent completion mark.

LNG Canada has also recently placed the 300+ tonne main cryogenic heat exchanger (MCHE) and two precooler units.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation but also South Korea’s Kogas.

LNG Canada expects the first LNG shipment from the first phase of the plant, which includes two trains with a capacity of 14 mtpa, in the middle of the decade.

Most Popular

Shell’s LNG Canada achieves first LNG

LNG giant Shell has started production at the first liquefaction train at its LNG Canada export terminal in Kitimat, an LNG Canada spokesperson told LNG Prime on Sunday.

Atlantic LNG shipping rates jump to $49,750 per day

Atlantic spot LNG shipping rates rose to $49,750 per day this week, while European prices also jumped compared to the previous week.

India’s May LNG imports drop

India's liquefied natural gas (LNG) imports dropped by 15.3 percent year-on-year in May, preliminary data from the oil ministry’s Petroleum Planning and Analysis Cell shows.

More News Like This

Shell’s LNG Canada achieves first LNG

LNG giant Shell has started production at the first liquefaction train at its LNG Canada export terminal in Kitimat, an LNG Canada spokesperson told LNG Prime on Sunday.

Shell’s LNG Canada nears first LNG

LNG giant Shell is nearing the launch of the first liquefaction train at its LNG Canada export terminal in Kitimat.

CFO: Shell on track to ship first LNG Canada cargo in middle of 2025

LNG giant Shell remains on track to deliver the first liquefied natural gas cargo from its LNG Canada export terminal in Kitimat in the middle of this year, according to Shell's finance chief, Sinead Gorman.

Chris Cooper takes over as LNG Canada CEO

Chris Cooper has taken over as president and chief executive officer of LNG Canada as the Shell-led JV prepares to ship the first LNG cargoes from the Kitimat facility.