Saipem does not expect Mozambique LNG work to resume this year

Italian contractor Saipem does not expect work on the TotalEnergies-led Mozambique LNG project to resume in 2022, according to its chief operating officer Alessandro Puliti.

France’s TotalEnergies declared force majeure on the $20 billion LNG project in April last year following new attacks, and withdrew all personnel from the site.

In February this year, TotalEnergies said it would not restart work on the project until the civil population comes back to the Cabo Delgado province where the Afungi site is located.

The project’s EPC contractor is CCS JV, a venture between Saipem, McDermott, and Chiyoda.

Saipem previously said that the firm had expected work to resume on the project this year.

However, the firm now does not see resumption of work prior to 2023. Saipem also said that the EPC contract would have to be amended due to surging costs.

“Our current costs are covered in a fully reimbursable scheme from the client and we do not expect any restart of operation within 2022,” Puliti told analysts on Wednesday during Saipem’s first-half results call.

“Completely different world”

CEO Francesco Caio said that compared to 2019 when the CCS JV won the Mozambique LNG contract, “we are in a completely different world today.”

This is due the Covid pandemic and “because of the inflation of the raw materials that we have been experiencing starting at the end of 2021, even before the beginning of the Ukrainian crisis,” he said.

He said that the costs and terms for the Mozambique contract would have to be changed, “because what was agreed back and the beginning of the project is clearly no longer sustainable.”

“So, their full restart of the project will be definitely on different basis, a renegotiated basis with the client,” Caio said.

Prior to this, TotalEnergies had expected to launch the Mozambique LNG project in 2024.

The project includes the development of offshore gas fields in Mozambique’s Area 1 and a 12.8 mtpa liquefaction plant at the Afungi complex.

Besides TotalEnergies, other partners in the project are Japan’s Mitsui, Mozambique’s ENH, Thailand’s PTT, and Indian firms ONGC, Bharat Petroleum, and Oil India.

- Advertisements -

Most Popular

Golden Pass LNG to speed up pipeline construction

QatarEnergy and ExxonMobil are seeking approval from US energy regulators to increase the peak workforce to speed up the...

US FERC to decide on Venture Global’s CP2 LNG project

The US FERC is set to decide next week on Venture Global LNG's proposed CP2 LNG project in Louisiana. According...

China’s Wison wins Indonesian FLNG gig from Genting

China's Wison New Energies has secured a contract from a unit of Genting to build a floating LNG unit...

More News Like This

TotalEnergies, NNPC take FID on new gas project to supply Nigeria LNG plant

France's TotalEnergies and Nigeria's NNPC have taken the final investment decision for the development of the Ubeta gas field...

Italy’s Eni sells 10 percent stake in Saipem

Italian energy firm Eni has sold a 10 percent stake in compatriot energy services company Saipem. Eni announced the...

TotalEnergies inks two Asian LNG supply deals

French energy giant TotalEnergies has entered into deals to supply liquefied natural gas (LNG) to Indian Oil and Korea...

India’s Dhamra LNG terminal received 20 cargoes in first year of operations

India’s Adani and France’s TotalEnergies have received 20 shipments at their Dhamra LNG import facility located in Odisha, on...