BP’s Tortue FLNG project on track to achieve first gas this year

BP’s Greater Tortue Ahmeyim FLNG project located offshore Mauritania and Senegal remains on track to achieve its first gas by the end of this year, according to project partner Kosmos Energy.

Texas-based Kosmos said in its quarterly results report that the construction work on the first phase of the Greater Tortue Ahmeyim LNG project “continues to make good progress”.

The project includes the conversion of Golar LNG’s Gimi to a floating LNG producer at Singapore’s Keppel shipyard, as well as the construction of an FPSO which has already left the yard in China.

Kosmos said that the FLNG construction and mechanical completion activities are finishing and commissioning work is underway.

Moreover, the partners expect the converted FLNG to depart from the yard mid-year 2023, the firm said.

The 2.5 mtpa Gimi FLNG will serve BP’s Greater Tortue Ahmeyim project under a 20-year deal.

Golar said in February that the conversion was about 92 percent technically complete.

FPSO to arrive end of Q2

The floating production, storage and offloading (FPSO) unit left Cosco Shipping Heavy Industry’s yard in Qidong, China in January this year.

It is currently in Singapore and “arrival on location offshore Mauritania/Senegal is expected around the end of the second quarter of 2023 when the hookup and commissioning work will commence,” Kosmos said.

Following arrival at the project site and completion of commissioning activities, the FPSO will process natural gas – removing condensate, water, and other impurities – before exporting it by pipeline to the project’s FLNG facilities, 10km offshore.

With eight processing and production modules, the FPSO will process around 500 million standard cubic feet of gas per day.

The FLNG will liquefy majority of the gas, enabling export to international markets, while some of the supplies will help meet growing demand in the two host countries, BP previously said.

Besides the FPSO, Kosmos said that laying of the deepwater section of the pipeline from the field to the unit is currently underway.

“This will be followed by the installation of the infield flowlines and subsea structures. Timely execution of this subsea work scope is the critical path to first gas by the end of the year,” the firm said.

Second phase

In February, BP and partners confirmed the development concept for the second phase of the GTA LNG project that they will take forward to the next stage of evaluation.

The partnership, composed of BP, Petrosen, SMH, and Kosmos will evaluate a gravity-based structure (GBS) as the basis for the GTA Phase 2 expansion project with total capacity of between 2.5-3 million tonnes per annum.

The concept design will also include new wells and subsea equipment, integrating with and expanding on existing GTA infrastructure.

In addition, the partners will consider powering liquefication using electricity to help drive operational emissions lower.

Kosmos said that the partners are finalizing decisions to move the project into pre-FEED.

Most Popular

Singfar orders LNG bunkering duo in China

Singapore-based shipowner Singfar has ordered two large LNG bunkering vessels from China's Huangpu Wenchong Shipbuilding.

Precious Shipping’s new Malaysian JV targets LNG and LPG carriers

Precious Shipping's new Malaysian joint venture with Emstraits Navigation and Lianson Fleet Group will be looking to acquire liquefied natural gas (LNG), liquefied petroleum gas (LPG), and crude tankers.

Noatum Maritime welcomes first LNG-powered PCTC in its fleet

AD Ports Group’s Noatum Maritime has taken delivery of its first LNG-powered pure car and truck carrier (PCTC).

More News Like This

Golar seals $1.2 billion leasing deal for FLNG Gimi

Floating LNG player Golar LNG has entered into lease agreements with a consortium of Chinese leasing companies for the refinancing of the existing FLNG Gimi debt facility.

BP exercises option to terminate charter deal for Seapeak LNG carrier

A unit of UK-based energy giant BP has exercised its option to terminate the existing charter deal for one of Seapeak's liquefied natural gas (LNG) carriers.

Golar in advanced FLNG charter talks

Floating LNG player Golar LNG is in advanced talks to secure a charter deal for its MKII FLNG, while it continues to work on further FLNG fleet expansion.

BP, partners near first Tortue LNG cargo

UK-based energy giant BP and its partners are close to shipping the first liquefied natural gas (LNG) cargo produced at the Greater Tortue Ahmeyim FLNG project, located offshore Mauritania and Senegal.