Cheniere’s Corpus Christi LNG expansion project almost 53 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 53 percent complete, and the US LNG exporting giant is working to start production at the first train later this year.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and compatriot Bechtel officially started construction on the project in October the same year.

The project was 51.4 percent complete in December last year.

It includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the January construction report filed with the US FERC last week that overall project completion for the Stage 3 project is 52.7 percent.

Stage 3 engineering and procurement are 86 percent and 72.9 percent complete, respectively, while subcontract and direct hire construction work are 69.5 percent and 12.3 percent complete, respectively.

Cheniere’s Corpus Christi LNG expansion project almost 53 complete
Image: Cheniere

First train work continues to progress

During January, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work and mobilization of temporary facilities, equipment.

Piling activities continued in trains 5 and 6. Concrete work in train 1 is “significantly complete” and underway in train 2, train 3, and OSBL, the company said.

Moreover, structural steel in train 1 is over halfway complete and has started in train 2 and OSBL, it said.

Underground piping is progressing in train 1, 2, 3, and OSBL and has started in train 4, while aboveground piping is progressing in train 1, train 2, and OSBL West.

CCL said equipment setting is ongoing in Train 1 and Train 2.

Cheniere’s Corpus Christi LNG expansion project almost 53 complete
Train 2 regen gas compressor set

First LNG production by end of 2024

Cheniere initially said that LNG deliveries from the expansion project were expected to begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

The company also confirmed in its 2023 report that it that it expects to achieve first LNG production from the first train at the end of 2024.

Besides this expansion, Cheniere plans to build two more liquefaction trains as part of the third expansion phase at the Corpus Christi plant.

The firm’s results show that it aims to take a final investment decision on CCL midscale trains 8 and 9 in 2025, subject to regulatory approvals.

In addition, Cheniere also aims to build two new liquefaction trains as part of the Sabine Pass Stage 5 expansion project to add up to 20 mtpa of capacity to the giant facility.

Cheniere plans to take FID on this project in 2026, subject to regulatory approvals.

Most Popular

Venture Global reveals LNG fleet details

US LNG exporter Venture Global LNG has revealed more details regarding its fleet of nine owned and three chartered liquefied natural gas carriers.

NFE working on two more FSRU charter deals

US LNG player New Fortress Energy is in advanced talks to charter two more floating and regasification units, according to its management.

CEO: Venture Global to sign multiple 20-year LNG contracts in coming quarters

US LNG exporter Venture Global LNG expects to sign and report on multiple 20-year LNG supply contracts in the incoming quarters, according to CEO Mike Sabel.

More News Like This

Cheniere nears first LNG at second Corpus Christi expansion train

Cheniere's CEO, Jack Fusco, expects the company to achieve first LNG at the second train of the Corpus Christi Stage 3 expansion project in Texas later this month or at the beginning of June.

Cheniere reports higher Q1 revenue

US LNG exporting giant Cheniere reported a rise in its quarterly revenue due to higher prices, while its net profit decreased compared to the same period last year.

Cheniere to introduce fuel gas to second Corpus Christi LNG expansion train

US LNG exporter Cheniere is nearing the introduction of fuel gas to the second train of the Corpus Christi Stage 3 expansion project in Texas as part of the commissioning phase.

Cheniere’s Corpus Christi expansion project 82.5 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 82.5 percent complete.