ExxonMobil says Golden Pass plant on track to deliver first LNG in H1 2025

Energy giants QatarEnergy and ExxonMobil are still expecting to start LNG production at their Golden Pass LNG export terminal on the US Gulf Coast near Sabine Pass, Texas, in the first half of 2025.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

“Train 1 mechanical completion is expected at the end of 2024 with first LNG in the first half of 2025,” Darren Woods, chairman and CEO of ExxonMobil, said during the fourth-quarter earnings call on February 2.

Woods did not provide further information.

He confirmed an announcement in December by ExxonMobil’s senior VP and CFO, Kathryn Mikellss, during the company’s corporate plan that first LNG is expected in first half of 2025.

The partners previously expected to complete the first Golden Pass train in the first quarter of 2024.

The US FERC said in an inspection report in January this year that the anticipated in-service timing for the first Golden Pass train is the second half of 2024,with train 2 and 3 following after.

According to the report, the anticipated in-service timing for the pipeline expansion project is expected “sometime prior to the second half of 2024”.

Construction update

Golden Pass LNG Terminal and Golden Pass Pipeline also recently filed the latest construction report with the FERC.

The report said that Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas and flare wall modifications, continued piping and vessels insulation activities, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins in Trains 2 and 3, and progressed brownfield tie-ins and LNG tank tops modifications scope.

Golden Pass also progressed cable tray installations and cable pulling activities and continued pipe pneumatic / hydrostatic testing program.

As per the pipeline expansion project, Golden Pass continued civil activities and concrete foundation pours at milepost MP33 and MP69 compressor stations and also continued pipe fabrication and installation at these stations.

It also continued construction activities of the Sabine Spur, Natural Gas Pipeline (NGPL)
Interconnect improvements, and associated facilities.

Most Popular

NFE expects to resolve Puerto Rico LNG supply dispute after Altamira LNG returns to service

US LNG player New Fortress Energy said Monday that it continues to discuss LNG supply disruptions with Puerto Rico and believes the issue will be resolved after its Fast LNG (FLNG) project off Mexico’s Altamira returns to service.

Samsung Heavy clinches LNG carrier order

South Korean shipbuilding giant Samsung Heavy Industries has secured an order to build one liquefied natural gas (LNG) carrier for approximately $257 million.

Knutsen takes delivery of tenth QatarEnergy LNG carrier

Norwegian shipowner Knutsen has taken delivery of another 174,000-cbm LNG carrier built as part of the massive QatarEnergy shipbuilding program.

More News Like This

Knutsen takes delivery of tenth QatarEnergy LNG carrier

Norwegian shipowner Knutsen has taken delivery of another 174,000-cbm LNG carrier built as part of the massive QatarEnergy shipbuilding program.

Orlen terminates QatarEnergy LNG supply contract

Poland’s Orlen said it had exercised its right to terminate one of the two long-term LNG supply contracts with a unit state-owned LNG giant QatarEnergy due to an ongoing force majeure resulting in an inability to meet contractual delivery obligations.

ExxonMobil boosts Rovuma LNG stake

US energy giant ExxonMobil has increased its stake in the planned Rovuma LNG project in Mozambique through a deal with Italy's Eni, while the company still targets a final investment decision by the end of this year, according to ExxonMobil CEO Darren Woods.

Technip Energies ready to hand over first NFE LNG train to QatarEnergy

French LNG engineer Technip Energies is ready to hand over the first train of the North Field East LNG project in Qatar to state-owned LNG giant QatarEnergy, while the second train has already started commissioning, according to Technip Energies CEO Arnaud Pieton.