LNG Canada pipeline almost 60 percent done

TC Energy’s Coastal GasLink pipeline project, which will supply natural gas to the Shell-led LNG Canada export terminal, has almost reached the 60 percent completion mark.

“This year, we start construction with almost 60 percent of the project completed, with Sections 1 and 4 nearing 100 percent completion,” Coastal GasLink said in an update.

According to the firm, the overall progress had reached 59.2 percent, as it continues to work towards its target completion date in 2023.

In November, it reached the 50 percent completion mark on the 670 km long pipeline.

“Most recently, we celebrated the safe completion of the Salmon River DPI water crossing with zero safety incidents. In the same construction section, we also saw the demobilization of the Vanderhoof Lodge, which at its peak housed over 869 workers,” Coastal GasLink said.

In total, 4,105 workers were working across the project route as of December 31.

LNG Canada pipeline almost 60 percent done
Image: Coastal GasLink

The pipeline has a price tag of more than C$6.6 billion ($5.18 billion). However, Coastal GasLink and LNG Canada previously said they were in commercial discussions regarding the cost and schedule for the project.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat, British Columbia.

LNG Canada also passed the 50 percent completion mark and installed the main absorber column. A large module is also on its way to Kitimat from China.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation but also South Korea’s Kogas.

LNG Canada expects the first LNG shipment from the first phase of the plant, which includes two trains with a capacity of 14 mtpa, in the middle of the decade.

Most Popular

K Line, Petronas name LNG carrier duo in China

Chinese shipbuilder Hudong-Zhonghua has hosted a naming ceremony for two 174,000-cbm liquefied natural gas (LNG) carriers it built for Japan’s K Line and Malaysia’s Petronas.

Japan’s MOL merges six ship management companies into one entity

Japanese shipping giant MOL, owner of a large LNG carrier fleet, has merged six of its ship management companies...

Atlantic spot LNG rates rise for first time in seven weeks

Atlantic spot LNG shipping rates rose for the first time in seven weeks, rising $3,750 week-on-week to $15,500 per day, according to Spark Commodities.

More News Like This

Peru LNG sent five shipments in August

Peru LNG’s liquefaction plant at Pampa Melchorita shipped five liquefied natural gas cargoes in July, the same as in the previous three months, according to shipment data by state-owned Perupetro.

Shell wraps up $16.5 billion ARC acquisition

UK-based LNG giant Shell has completed its previously announced acquisition of Canadian gas producer ARC Resources for $16.5 billion, including debt, after receiving all required shareholder, court, and regulatory approvals.

Wison strengthens its FLNG offering with Shell deal

Chinese FLNG builder Wison New Energies has signed a collaboration agreement to integrate Shell’s liquefaction technology into its floating...

Shell, partners take FID on new project to deliver more gas to Egypt

Egypt, which has turned to LNG imports over the last two years to cover domestic natural gas shortages, will receive more much-needed gas supplies after UK-based LNG giant Shell and its partners took a final investment decision on the Phase 12a development project in the West Delta Deep Marine (WDDM) concession.