LNG Canada pipeline almost 60 percent done

TC Energy’s Coastal GasLink pipeline project, which will supply natural gas to the Shell-led LNG Canada export terminal, has almost reached the 60 percent completion mark.

“This year, we start construction with almost 60 percent of the project completed, with Sections 1 and 4 nearing 100 percent completion,” Coastal GasLink said in an update.

According to the firm, the overall progress had reached 59.2 percent, as it continues to work towards its target completion date in 2023.

In November, it reached the 50 percent completion mark on the 670 km long pipeline.

“Most recently, we celebrated the safe completion of the Salmon River DPI water crossing with zero safety incidents. In the same construction section, we also saw the demobilization of the Vanderhoof Lodge, which at its peak housed over 869 workers,” Coastal GasLink said.

In total, 4,105 workers were working across the project route as of December 31.

LNG Canada pipeline almost 60 percent done
Image: Coastal GasLink

The pipeline has a price tag of more than C$6.6 billion ($5.18 billion). However, Coastal GasLink and LNG Canada previously said they were in commercial discussions regarding the cost and schedule for the project.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat, British Columbia.

LNG Canada also passed the 50 percent completion mark and installed the main absorber column. A large module is also on its way to Kitimat from China.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation but also South Korea’s Kogas.

LNG Canada expects the first LNG shipment from the first phase of the plant, which includes two trains with a capacity of 14 mtpa, in the middle of the decade.

Most Popular

Venture Global kicks off CP2 LNG site work

US LNG exporter Venture Global said it had initiated full mobilization and started site work at the company’s third LNG export facility, CP2 LNG.

Purus orders LNG carrier in South Korea

London-based Purus Marine has ordered one 180,000-cbm liquefied natural gas (LNG) carrier in South Korea.

Excelerate advances Vietnam LNG talks

US FSRU player Excelerate Energy is moving forward with its plans to supply Vietnam with liquefied natural gas (LNG) supplies from the US.

More News Like This

Shell takes FID on Aphrodite project to supply Trinidad’s Atlantic LNG

A unit of UK-based LNG giant Shell has taken the final investment decision for the development of the Aphrodite gas field to supply Trinidad and Tobago’s Atlantic LNG export plant.

Peru LNG terminal shipped five cargoes in May

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped five liquefied natural gas cargoes in May, two more than in the previous month.

Shell shareholders re-elect CEO Wael Sawan

Wael Sawan will continue to lead London-based LNG giant Shell following shareholder voting at the company's annual general meeting on Tuesday.

Singapore’s FueLNG wraps up 400th STS bunkering operation

Singapore’s FueLNG, a joint venture consisting of Shell and Seatrium, has completed its 400th ship-to-ship (STS) LNG bunkering operation. FuelLNG delivered LNG to BYD Shenzen, which is said to be the world’s largest LNG-fueled car carrier.