LNG Canada pipeline almost 60 percent done

TC Energy’s Coastal GasLink pipeline project, which will supply natural gas to the Shell-led LNG Canada export terminal, has almost reached the 60 percent completion mark.

“This year, we start construction with almost 60 percent of the project completed, with Sections 1 and 4 nearing 100 percent completion,” Coastal GasLink said in an update.

According to the firm, the overall progress had reached 59.2 percent, as it continues to work towards its target completion date in 2023.

In November, it reached the 50 percent completion mark on the 670 km long pipeline.

“Most recently, we celebrated the safe completion of the Salmon River DPI water crossing with zero safety incidents. In the same construction section, we also saw the demobilization of the Vanderhoof Lodge, which at its peak housed over 869 workers,” Coastal GasLink said.

In total, 4,105 workers were working across the project route as of December 31.

LNG Canada pipeline almost 60 percent done
Image: Coastal GasLink

The pipeline has a price tag of more than C$6.6 billion ($5.18 billion). However, Coastal GasLink and LNG Canada previously said they were in commercial discussions regarding the cost and schedule for the project.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat, British Columbia.

LNG Canada also passed the 50 percent completion mark and installed the main absorber column. A large module is also on its way to Kitimat from China.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation but also South Korea’s Kogas.

LNG Canada expects the first LNG shipment from the first phase of the plant, which includes two trains with a capacity of 14 mtpa, in the middle of the decade.

- Advertisements -

Most Popular

Commissioning of India’s Chhara LNG terminal delayed

India’s Hindustan Petroleum, a unit of state-owned ONGC, has reportedly delayed the commissioning of its Chhara LNG import terminal...

MOL’s LNG carrier fleet to grow to 104 vessels by March 2025

Japan's shipping giant MOL expects its huge fleet of liquefied natural gas (LNG) carriers to increase to 104 vessels...

Venture Global: Plaquemines LNG to start production in mid-2024

US LNG exporter Venture Global LNG expects to start LNG production at its Plaquemines LNG export plant in Louisiana...

More News Like This

Shell’s Q1 profit drops to $7.73 billion, LNG sales slightly down

LNG giant Shell reported a decrease of 19.8 percent in its adjusted earnings in the first quarter this year,...

Oman LNG delivered 173 cargoes last year, revenue reached $4.9 billion

State-owned Oman LNG delivered 173 cargoes of liquefied natural gas from its Qalhat complex in 2023, down by three...

Mitsui: no decision on Adnoc’s LNG project

Japan's trading house Mitsui & Co said nothing has been decided on an LNG project in the United Arab...

Shell launches largest bio-LNG plant in Germany

A unit of LNG giant Shell has launched what it says is the largest bio-LNG production plant in Germany. The...