Cheniere’s Corpus Christi LNG expansion project almost 53 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 53 percent complete, and the US LNG exporting giant is working to start production at the first train later this year.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and compatriot Bechtel officially started construction on the project in October the same year.

The project was 51.4 percent complete in December last year.

It includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the January construction report filed with the US FERC last week that overall project completion for the Stage 3 project is 52.7 percent.

Stage 3 engineering and procurement are 86 percent and 72.9 percent complete, respectively, while subcontract and direct hire construction work are 69.5 percent and 12.3 percent complete, respectively.

Cheniere’s Corpus Christi LNG expansion project almost 53 complete
Image: Cheniere

First train work continues to progress

During January, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work and mobilization of temporary facilities, equipment.

Piling activities continued in trains 5 and 6. Concrete work in train 1 is “significantly complete” and underway in train 2, train 3, and OSBL, the company said.

Moreover, structural steel in train 1 is over halfway complete and has started in train 2 and OSBL, it said.

Underground piping is progressing in train 1, 2, 3, and OSBL and has started in train 4, while aboveground piping is progressing in train 1, train 2, and OSBL West.

CCL said equipment setting is ongoing in Train 1 and Train 2.

Cheniere’s Corpus Christi LNG expansion project almost 53 complete
Train 2 regen gas compressor set

First LNG production by end of 2024

Cheniere initially said that LNG deliveries from the expansion project were expected to begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

The company also confirmed in its 2023 report that it that it expects to achieve first LNG production from the first train at the end of 2024.

Besides this expansion, Cheniere plans to build two more liquefaction trains as part of the third expansion phase at the Corpus Christi plant.

The firm’s results show that it aims to take a final investment decision on CCL midscale trains 8 and 9 in 2025, subject to regulatory approvals.

In addition, Cheniere also aims to build two new liquefaction trains as part of the Sabine Pass Stage 5 expansion project to add up to 20 mtpa of capacity to the giant facility.

Cheniere plans to take FID on this project in 2026, subject to regulatory approvals.

Most Popular

Jera boosts Wheatstone LNG stake

Japan’s power firm and LNG trader, Jera, has strengthened its indirect stake in the Chevron-operated Wheatstone LNG project in Australia by acquiring additional shares.

Taiwan’s CPC makes progress with Alaska LNG deal

Taiwan’s CPC Corp is making progress on buying LNG and investing in the planned Glenfarne-led Alaska LNG project, according to Taiwan's economy ministry.

Shell, GTT, and LR to develop new LNG carrier

UK-based LNG giant Shell, French LNG containment specialist GTT, and classification society Lloyd’s Register have launched a joint development project to develop a conceptual 200,000-cbm LNG carrier combining hybrid-electric propulsion with GTT’s Next1 LNG cargo containment technology.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project 55.6 percent complete

US LNG exporter Cheniere continues to progress construction on its Corpus Christi Midscale Trains 8 and 9 project in Texas.

Cheniere, Petrobras seal long-term LNG SPA

US LNG exporter Cheniere has signed a long-term LNG sale and purchase agreement with Brazil’s state-owned energy firm Petrobras

US FERC issues final EIS for Cheniere’s Sabine Pass expansion project

The US Federal Energy Regulatory Commission (FERC) has released a final environmental impact statement for Cheniere’s planned Sabine Pass Stage 5 expansion project. The regulator confirmed that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”

FERC issues draft EIS for Cheniere’s Corpus Christi Stage 4 project

The US Federal Energy Regulatory Commission (FERC) has released a draft environmental impact statement for Cheniere’s planned Corpus Christi Liquefaction Stage IV expansion project in Texas. The regulator concluded that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”