Cheniere’s third Sabine Pass LNG jetty almost complete

US LNG exporting giant Cheniere and compatriot Bechtel have almost completed the third jetty project at the six-train 30 mtpa Sabine Pass LNG facility in Louisiana.

According to the latest construction update filed with FERC, the third jetty project was 99.1 percent complete as of August this year, compared to 96.4 percent in July.

“Currently, engineering, procurement, and subcontracts are 100 percent complete against the plan of 100 percent, and construction is 97.5 percent complete against the plan of 97.2 percent,” Cheniere said in the update.

Cheniere started commissioning of the third jetty’s LNG loading arms in August.

“Final preparations for the introduction of hydrocarbons and cooldown commenced and are on track to finish in early September,” it said.

According to Cheniere, it plans to complete commissioning of LNG transfer arms during September.

It appears that the third jetty has already welcomed at least one LNG tanker.

The 174,000-cbm LNG carriers, Aristarchos, owned by Capital Product Partners and chartered by Cheniere, visited the new berth earlier this month, its AIS data shows.

VesselsValue data shows that the vessel was on Friday located at Elengy’s Montoir-de-Bretagne LNG import terminal in France.

Boosting capacity

Cheniere and compatriot Bechtel are adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

Moreover, it will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at Cheniere’s plant by 180 per year.

The operator of the Sabine Pass and Corpus Christi terminals recently revealed plans to increase the company’s liquefaction capacity to about 90 mtpa as part of its “20/20 Vision” long-term capital allocation plan.

Also, Cheniere recently took a final investment decision on Stage 3 expansion at its Corpus Christi LNG export plant in Texas.

The expansion will add about 10 mtpa to the three-train 15 mtpa Corpus Christi plant.

Most Popular

Taiwan’s CPC inks initial Alaska LNG deal

Taiwan’s CPC Corp has signed a letter of intent with Alaska Gasline Development Corporation (AGDC) to buy LNG and invest in the latter's planned Alaska LNG project.

Woodside updates on Louisiana LNG construction work

Australian LNG producer Woodside has released the latest construction update for the first phase of its Louisiana LNG project.

DET terminates Stade FSRU contract with HEH

State-owned German LNG terminal operator DET has terminated the contract related to the Stade FSRU-based facility with compatriot Hanseatic Energy Hub, the developer of the onshore LNG terminal in Stade.

More News Like This

Cheniere completes first train at Corpus Christi expansion project

US LNG exporting giant Cheniere has achieved substantial completion of the first liquefaction train at the Corpus Christi Stage 3 expansion project in Texas.

Cheniere gets FERC OK for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere has received approval from the US FERC to build two more midscale trains at its Corpus Christi LNG plant in Texas.

Corpus Christi LNG expansion project 78.3 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 78.3 percent complete.

Cheniere targets Sabine Pass LNG expansion FID in 2026 or 2027

US LNG exporting giant Cheniere plans to make a final investment decision to expand its giant Sabine Pass LNG plant in Louisiana in late 2026 or 2027, according to its management.