LNG Canada pipeline almost 60 percent done

TC Energy’s Coastal GasLink pipeline project, which will supply natural gas to the Shell-led LNG Canada export terminal, has almost reached the 60 percent completion mark.

“This year, we start construction with almost 60 percent of the project completed, with Sections 1 and 4 nearing 100 percent completion,” Coastal GasLink said in an update.

According to the firm, the overall progress had reached 59.2 percent, as it continues to work towards its target completion date in 2023.

In November, it reached the 50 percent completion mark on the 670 km long pipeline.

“Most recently, we celebrated the safe completion of the Salmon River DPI water crossing with zero safety incidents. In the same construction section, we also saw the demobilization of the Vanderhoof Lodge, which at its peak housed over 869 workers,” Coastal GasLink said.

In total, 4,105 workers were working across the project route as of December 31.

LNG Canada pipeline almost 60 percent done
Image: Coastal GasLink

The pipeline has a price tag of more than C$6.6 billion ($5.18 billion). However, Coastal GasLink and LNG Canada previously said they were in commercial discussions regarding the cost and schedule for the project.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat, British Columbia.

LNG Canada also passed the 50 percent completion mark and installed the main absorber column. A large module is also on its way to Kitimat from China.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation but also South Korea’s Kogas.

LNG Canada expects the first LNG shipment from the first phase of the plant, which includes two trains with a capacity of 14 mtpa, in the middle of the decade.

Most Popular

Woodside terminates Commonwealth LNG SPA

Australian LNG player Woodside has terminated its two LNG sale and purchase agreements with US LNG terminal developer Commonwealth LNG.

Thailand in Alaska LNG talks

Thailand's PTT and Egco will engage in further discussions to potentially participate in the development and buy volumes from the planned Alaska LNG project, according to Thailand's Ministry of Energy.

Energy Transfer seals Lake Charles LNG supply deals

Texas-based Energy Transfer has signed new supply deals for its planned Lake Charles LNG export facility in Louisiana as it works to take a final investment decision by the end of this year, according to its management.

More News Like This

Peru LNG terminal shipped three cargoes in April

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped three liquefied natural gas cargoes in April due to restrictions on the transportation system, according to operator Hunt Oil.

CFO: Shell on track to ship first LNG Canada cargo in middle of 2025

LNG giant Shell remains on track to deliver the first liquefied natural gas cargo from its LNG Canada export terminal in Kitimat in the middle of this year, according to Shell's finance chief, Sinead Gorman.

Shell’s Q1 profit reaches $5.58 billion, LNG sales drop

LNG giant Shell reported a drop in adjusted earnings in the first quarter of 2025, while its LNG sales also decreased compared to the same quarter in 2024.

Venture Global launches Calcasieu Pass LNG commercial ops

US LNG exporter Venture Global LNG has launched commercial operations at its Calcasieu Pass LNG terminal in Louisiana, some 68 months from its final investment decision and 38 months after production start.