LNG Canada pipeline almost 60 percent done

TC Energy’s Coastal GasLink pipeline project, which will supply natural gas to the Shell-led LNG Canada export terminal, has almost reached the 60 percent completion mark.

“This year, we start construction with almost 60 percent of the project completed, with Sections 1 and 4 nearing 100 percent completion,” Coastal GasLink said in an update.

According to the firm, the overall progress had reached 59.2 percent, as it continues to work towards its target completion date in 2023.

In November, it reached the 50 percent completion mark on the 670 km long pipeline.

“Most recently, we celebrated the safe completion of the Salmon River DPI water crossing with zero safety incidents. In the same construction section, we also saw the demobilization of the Vanderhoof Lodge, which at its peak housed over 869 workers,” Coastal GasLink said.

In total, 4,105 workers were working across the project route as of December 31.

LNG Canada pipeline almost 60 percent done
Image: Coastal GasLink

The pipeline has a price tag of more than C$6.6 billion ($5.18 billion). However, Coastal GasLink and LNG Canada previously said they were in commercial discussions regarding the cost and schedule for the project.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat, British Columbia.

LNG Canada also passed the 50 percent completion mark and installed the main absorber column. A large module is also on its way to Kitimat from China.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation but also South Korea’s Kogas.

LNG Canada expects the first LNG shipment from the first phase of the plant, which includes two trains with a capacity of 14 mtpa, in the middle of the decade.

Most Popular

First Rio Grande LNG tank taking shape

US LNG developer NextDecade continues to make progress on the first phase of its Rio Grande LNG export plant in Texas, including the first 180,000-cbm storage tank.

Venture Global gets FERC OK to boost Plaquemines LNG capacity

US LNG exporter Venture Global LNG has received approval from the US FERC to boost the capacity of its Plaquemines LNG terminal in Louisiana to 27.2 mtpa.

Asyad Shipping sells LNG carrier

Oman's Asyad Shipping has sold a 2006-built steam liquefied natural gas (LNG) carrier, according to brokers.

More News Like This

Venture Global says to launch Calcasieu Pass LNG commercial ops in April

US LNG exporter Venture Global LNG expects to launch commercial operations at its Calcasieu Pass LNG terminal in Louisiana in April, some 68 months from its final investment decision and 38 months after production start.

BP chief expects ruling on Venture Global dispute later this year

BP's CEO Murray Auchincloss expects a ruling on an arbitration dispute with US LNG exporter Venture Global LNG to be delivered in the second half of this year.

Shell expects significant near-term LNG demand growth

UK-based LNG giant Shell expects significant LNG demand growth in the near term, fueled by ongoing projects in Qatar and the USA, according to a new report.

Peru LNG terminal sent three cargoes in January

According to the shipment data by state-owned Perupetro, during January, the 4.4 mtpa LNG plant sent two shipments to...