Canada’s Pembina says Cedar LNG FID may move into early 2024

Canada’s Pembina Pipeline and the Haisla Nation may move their planned final investment decision on the Cedar LNG export project from the fourth quarter of this year to early 2024.

In August, the partners postponed taking the decision from the third quarter to the fourth quarter.

Pembina and the Haisla Nation each own 50 percent in the Cedar LNG project.

Last year, US-based engineer Black & Veatch and South Korean shipbuilder Samsung Heavy Industries won the front-end engineering and design (FEED) contract for the project’s proposed floating liquefaction, storage and offloading unit (FLNG).

The $2.4 billion FLNG project will have a capacity of about 3 mtpa and will source natural gas from the prolific Montney resource play in northeast British Columbia.

Moreover, Cedar LNG plans to receive feed gas from the Coastal GasLink pipeline, which will supply the giant Shell-led LNG Canada export plant near Kitimat.

The floating LNG facility will also be located near the LNG Canada plant and will be powered by renewable electricity from BC Hydro.

Pembina said in its third-quarter report on Thursday that Cedar LNG “continues to progress key project deliverables”.

The project has secured the major regulatory approvals and signed non-binding memorandums of understanding for long-term liquefaction services with “investment grade counterparties” for the project’s total base liquefaction capacity, the firm said.

Pembina said remaining FID deliverables continue to progress, including finalizing the lump-sum engineering, procurement, and construction contract, the definitive liquefaction tolling agreements, and the inter-project agreements with Coastal GasLink and LNG Canada.

“Target FID continues to be by the end of 2023, however, given the complexity and sequencing of aligning the multiple work streams, which are required to facilitate the project financing, FID may move into early 2024,” Pembina said.

Most Popular

Construction moving forward on Golden Pass LNG terminal

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18...

Adnoc’s LNG carrier nears delivery in China

Adnoc's first 175,000-cbm LNG carrier, Al Shelila, has completed its sea trials in China, according to CSSC’s Jiangnan Shipyard. Jiangan...

Singapore LNG bunkering volumes continue to increase

Preliminary bunkering data on MPA’s website shows LNG bunkering sales in the world’s largest bunkering port reached 45,590 mt...

More News Like This

Pembina sees high interest in Cedar LNG volumes

In June, Pembina and the Haisla Nation took a positive final investment decision on the LNG project which is...

GTT scores tank gig for Canadian FLNG

French LNG containment giant GTT has secured a tank design order from South Korean shipbuilder Samsung Heavy for one...

Haisla Nation, Pembina take FID on $4 billion Cedar LNG project

Canada’s Pembina Pipeline and the Haisla Nation have taken a positive final investment decision on their $4 billion Cedar...

Steelhead LNG secures patents in US and South Korea

Vancouver-based Steelhead LNG has secured patents in the United States and South Korea for its proprietary near-shore floating LNG...